Current Progress

  • Internal metal partitions progress.
  • Continuation of mechanical and electrical works.
  • Works ongoing to the link bridge.

March 2020

Further progression of key internal construction works has been underway at Sky Gardens.

During the last few weeks, Sky Gardens construction continues internally. Metal partitions are being installed and mechanical and electrical works are still ongoing.

 

Summary of Works Progressed

  • Further progression to the internal metal partitions works.
  • Continuation of mechanical and electrical works.
  • Ongoing works to the link bridge.

Works Scheduled

  • TBA

December 2019

At Sky Gardens in Liverpool, completion of many tasks have been achieved whilst other construction activities such as metal partitioning and mechanical and electrical works are making great progress.

There has been significant progress to both internal and external works at the site. New windows have been successfully installed and strip out works are 100% complete whilst works to the link bridge, brick slip installation and external render all keep pushing this project forward towards completion.

 

Summary of Works Progressed

  • Completion of strip out works has been achieved.
  • Completion of new window installation.
  • Near completion of insulation installation.
  • Progression of the external render as brick slip installation continues.
  • Progression of metal partitioning works internally.
  • Progression of mechanical and electrical works internally.
  • Progression of works to link bridge.

Works Scheduled

  • Continued internal works including mechanical and electrical installation, link bridge and metal partitioning.

September 2019

In the latest Sky Gardens construction update, progress has been made across multiple areas of construction throughout the development.

Many areas of construction are complete and further advancements have begun, paving the way for more development over the coming months.

 

Summary of Works Progressed

  •  Windows are now 100% installed throughout the development and internal partitioning is underway on the upper floors.
  • Demolition of the safe room near to the rear block is also complete, as well as the structural alterations made to the brick and blockwork walls.
  • The steelwork vent supports have been installed for the smoke vent and floor apertures have been infilled where redundant.
  • Scaffolding has been erected to the rear block to allow the existing plant room to receive cladding.
  • Main entrance doors and screen are installed, while structural steel framing has also been installed and progress has been made to the cement particle boards to the under-croft areas of the development.
  • The installation of brick slip cladding has commenced and the insulation which precedes this is 100% complete. The internal boarding has also started to be installed.

 

Works Scheduled

  • TBA

June 2019

 Following on from the last Sky Gardens construction update, there are a number of advancements being made with the development.

This latest update outlines the progress made on strip out works, insulation and rendering, blockwork, and other structural elements.

 

Summary of Works Progressed

  • The removal of existing windows is underway, with blockwork being added to secure new windows.
  • Internal partitions are currently being installed.
  • Strip works, insulation and rendering of link building, and ceilings and soffits work has been completed.

 

 

 Works Scheduled

  •  Windows are scheduled to be installed.
  • Cladding work is yet to commence.
  • Internal fixings are scheduled for continuation.

March 2019

The latest Sky Gardens construction update from the developer mainly entails the progression of the remaining strip out works, ceilings and soffits, and partition walls.

Contractors continue to liaise all the final details and packages for the site, and ongoing progress will be made over the coming months.

 

Summary of Works Progressed

  • Partition walls, ceilings and soffits, and remaining strip out works have progressed,
  • The development of structural steelworks is underway.
  • The contractor continues to liaise with the envelope contractor with regards to the final details for Sky Gardens.
  • Works to the external façade have begun.

 

Works Scheduled

  • Disabled car parking spaces and electric vehicle charging points are to be incorporated within the external works package.
  • Ongoing progression of strip out works, ceilings and soffits and partition walls will continue.

December 2018

The latest construction update for Sky Gardens deals with the removal of asbestos from the resident entrance area, and the completion of internal strip out.

The site is now prepared for internal works to progress further into the New Year and for the external façade to begin.

 

Summary of Works Progressed

  • Large filter fans have been set up to exhaust asbestos particles from the air, with thorough sealing of the affected area. Anything containing asbestos materials has also been removed.
  • Stud walls and electrics have been installed to the upper floors.
  • Internal strip out is now complete and Window frames and cladding fixtures are now going up on the outside of the building.
  • The old lift has been de-commissioned and removed, and furniture removal is complete.

 

Works Scheduled

  • Internal works are on schedule and are due to progress in the New Year.
  • External façade works will commence into the New Year.

September 2018

The latest Sky Gardens Construction Update details the setup of the site plus extensive strip out and removal of materials from the location to make way for new structures.

Main works include the removal of electrical fittings, the stripping out of ceilings, and the elimination of surplus materials.

 

Summary of Works Progressed

  • A full survey of the building and roof has been undertaken, scaffold erection is underway, and site hoarding is up.
  • Materials continue to be removed from the site and the removal of electrical fittings continues.
  • The fire strategy has been produced.
  • Internal strip out is nearing completion while ceiling strip outs continue to progress, with ceiling zones being cleaned out.

 

Works Scheduled

  • Further asbestos removal and remediation works will be carried out.
  • Window frames and other structural features are to be added, and progress with electrical structures will be made.

June 2018

Things are progressing well for the construction of the Sky Gardens development.

By June 2018, progress has been made in terms of design, planning, structural, mechanical and electrical works, and main contract works. The site is being well prepared for construction, with the removal of on-site materials and internal structures and fittings.

 

Summary of Works Progressed

  • Materials are being removed via skips on-site, along with the ongoing removal of the internal studwork and electrical fittings and the carpet and floor tile finishes. The removal of toilet cubicles and vanity units has also progressed.
  • The site hoarding has been erected, while internal strip out and ceiling strip outs continue to progress.
  • A full survey of the existing building has been carried out by the structural engineer. This includes pulling testing of the concrete structure of both the front and rear block in relation to supporting the new cladding system.
  • A survey has taken place to establish the incoming services, including electrics, water, telecoms and gas. The M&E engineer is working with the architect to finalise the relocation of the existing connections. A survey of the existing lift and lift shaft has also taken place.
  • The design team have been continuing to work together to finalise the designs with final plans nearing completion.
  • A drainage survey has been completed and alteration works have progressed.

 

Works Scheduled

  • A further asbestos survey is underway with any remediation works to also be carried out.
  • One of the current lifts needs to be a fire fighting lift. The M&E engineer is sourcing a suitable lift from lift manufacturers.
  • The current utility connections are to be disconnected and temporary supply provided.

2020

March

March 2020

Further progression of key internal construction works has been underway at Sky Gardens.

During the last few weeks, Sky Gardens construction continues internally. Metal partitions are being installed and mechanical and electrical works are still ongoing.

 

Summary of Works Progressed

  • Further progression to the internal metal partitions works.
  • Continuation of mechanical and electrical works.
  • Ongoing works to the link bridge.

Works Scheduled

  • TBA

2019

December

December 2019

At Sky Gardens in Liverpool, completion of many tasks have been achieved whilst other construction activities such as metal partitioning and mechanical and electrical works are making great progress.

There has been significant progress to both internal and external works at the site. New windows have been successfully installed and strip out works are 100% complete whilst works to the link bridge, brick slip installation and external render all keep pushing this project forward towards completion.

 

Summary of Works Progressed

  • Completion of strip out works has been achieved.
  • Completion of new window installation.
  • Near completion of insulation installation.
  • Progression of the external render as brick slip installation continues.
  • Progression of metal partitioning works internally.
  • Progression of mechanical and electrical works internally.
  • Progression of works to link bridge.

Works Scheduled

  • Continued internal works including mechanical and electrical installation, link bridge and metal partitioning.
September

September 2019

In the latest Sky Gardens construction update, progress has been made across multiple areas of construction throughout the development.

Many areas of construction are complete and further advancements have begun, paving the way for more development over the coming months.

 

Summary of Works Progressed

  •  Windows are now 100% installed throughout the development and internal partitioning is underway on the upper floors.
  • Demolition of the safe room near to the rear block is also complete, as well as the structural alterations made to the brick and blockwork walls.
  • The steelwork vent supports have been installed for the smoke vent and floor apertures have been infilled where redundant.
  • Scaffolding has been erected to the rear block to allow the existing plant room to receive cladding.
  • Main entrance doors and screen are installed, while structural steel framing has also been installed and progress has been made to the cement particle boards to the under-croft areas of the development.
  • The installation of brick slip cladding has commenced and the insulation which precedes this is 100% complete. The internal boarding has also started to be installed.

 

Works Scheduled

  • TBA
June

June 2019

 Following on from the last Sky Gardens construction update, there are a number of advancements being made with the development.

This latest update outlines the progress made on strip out works, insulation and rendering, blockwork, and other structural elements.

 

Summary of Works Progressed

  • The removal of existing windows is underway, with blockwork being added to secure new windows.
  • Internal partitions are currently being installed.
  • Strip works, insulation and rendering of link building, and ceilings and soffits work has been completed.

 

 

 Works Scheduled

  •  Windows are scheduled to be installed.
  • Cladding work is yet to commence.
  • Internal fixings are scheduled for continuation.
March

March 2019

The latest Sky Gardens construction update from the developer mainly entails the progression of the remaining strip out works, ceilings and soffits, and partition walls.

Contractors continue to liaise all the final details and packages for the site, and ongoing progress will be made over the coming months.

 

Summary of Works Progressed

  • Partition walls, ceilings and soffits, and remaining strip out works have progressed,
  • The development of structural steelworks is underway.
  • The contractor continues to liaise with the envelope contractor with regards to the final details for Sky Gardens.
  • Works to the external façade have begun.

 

Works Scheduled

  • Disabled car parking spaces and electric vehicle charging points are to be incorporated within the external works package.
  • Ongoing progression of strip out works, ceilings and soffits and partition walls will continue.

2018

December

December 2018

The latest construction update for Sky Gardens deals with the removal of asbestos from the resident entrance area, and the completion of internal strip out.

The site is now prepared for internal works to progress further into the New Year and for the external façade to begin.

 

Summary of Works Progressed

  • Large filter fans have been set up to exhaust asbestos particles from the air, with thorough sealing of the affected area. Anything containing asbestos materials has also been removed.
  • Stud walls and electrics have been installed to the upper floors.
  • Internal strip out is now complete and Window frames and cladding fixtures are now going up on the outside of the building.
  • The old lift has been de-commissioned and removed, and furniture removal is complete.

 

Works Scheduled

  • Internal works are on schedule and are due to progress in the New Year.
  • External façade works will commence into the New Year.
September

September 2018

The latest Sky Gardens Construction Update details the setup of the site plus extensive strip out and removal of materials from the location to make way for new structures.

Main works include the removal of electrical fittings, the stripping out of ceilings, and the elimination of surplus materials.

 

Summary of Works Progressed

  • A full survey of the building and roof has been undertaken, scaffold erection is underway, and site hoarding is up.
  • Materials continue to be removed from the site and the removal of electrical fittings continues.
  • The fire strategy has been produced.
  • Internal strip out is nearing completion while ceiling strip outs continue to progress, with ceiling zones being cleaned out.

 

Works Scheduled

  • Further asbestos removal and remediation works will be carried out.
  • Window frames and other structural features are to be added, and progress with electrical structures will be made.
June

June 2018

Things are progressing well for the construction of the Sky Gardens development.

By June 2018, progress has been made in terms of design, planning, structural, mechanical and electrical works, and main contract works. The site is being well prepared for construction, with the removal of on-site materials and internal structures and fittings.

 

Summary of Works Progressed

  • Materials are being removed via skips on-site, along with the ongoing removal of the internal studwork and electrical fittings and the carpet and floor tile finishes. The removal of toilet cubicles and vanity units has also progressed.
  • The site hoarding has been erected, while internal strip out and ceiling strip outs continue to progress.
  • A full survey of the existing building has been carried out by the structural engineer. This includes pulling testing of the concrete structure of both the front and rear block in relation to supporting the new cladding system.
  • A survey has taken place to establish the incoming services, including electrics, water, telecoms and gas. The M&E engineer is working with the architect to finalise the relocation of the existing connections. A survey of the existing lift and lift shaft has also taken place.
  • The design team have been continuing to work together to finalise the designs with final plans nearing completion.
  • A drainage survey has been completed and alteration works have progressed.

 

Works Scheduled

  • A further asbestos survey is underway with any remediation works to also be carried out.
  • One of the current lifts needs to be a fire fighting lift. The M&E engineer is sourcing a suitable lift from lift manufacturers.
  • The current utility connections are to be disconnected and temporary supply provided.
parallax-image

Find your Ideal Investment Property

Start Search

Best of Both Worlds

With Liverpool’s city centre easily accessible, and a surrounding relaxed area of shops, bars and restaurants, the Sky Gardens apartments give tenants the chance to experience a calmer, suburban lifestyle while still benefiting from all the perks of being close to the city. The closeby Waterloo station provides regular fast access into the heart of the city centre, and the property is also only a few minutes away from Crosby Marina and Crosby Beach.

A Rising Area

Ranked in the Top Five Places to Live in the North West by the Sunday Times, Crosby is a promising and trendy area that is proving popular among both tenants and investors. The area has and will continue to sustain growth over the coming years, and much like the city itself, the rental yield and growth prospects are trending positively.

Crosby, and its neighbouring areas of Bootle, Southport and Formby, are all experiencing positive growth. For more information on Crosby, or any other investment areas in the UK, get in touch with our team today.

 

What do we offer?

buildings

Hands Off
Investments

price

Below Market
Value Prices

growth

High Rental
Returns

growth icon

Potential for
Capital Appreciation