ELEMENT – The Quarter Construction Updates

The Latest on ELEMENT - The Quarter

ELEMENT – The Quarter is the first eco development in Liverpool, brought to the market by RWinvest and Nexus Residential. This development welcomes both postgraduate students and professionals into luxury accommodation in Liverpool with amazing onsite facilities. Here are all of the latest ELEMENT – The Quarter construction updates:

  • Apartment ceiling installation is 50% complete
  • External wall insulation and render is 75% progressed
  • Bathroom sanitary fittings are 45% complete

Lift installation has now commenced at ELEMENT – The Quarter, with other internal works racing ahead.

1st and 2nd fix electrical, plumbing and heating works are all making great progress. Carpet and floor finishes are making excellent headway, as well as plaster finishes to walls and ceiling, doorframes, skirting and architrave.

Summary of Works Progressed 

  • Retaining walls and concrete beam foundations are now 85% complete
  • Underground drainage is 99% progressed
  • Scaffolding and mast climber access has achieved 99% progression so far
  • Development to the flat roof covering including balconies is 89% complete
  • Weatherboarding is 87% complete
  • External windows, doors and curtain walling are 80% progressed
  • External wall insulation and render is 75% progressed
  • The Mansafe system is 60% complete
  • The lift has been installed to 40%
  • Partition wall installation is 69% complete
  • Apartment ceiling installation is 50% complete
  • Plaster finishes to walls and ceilings are now 55% progressed
  • 1st fix electrical is 86% progressed with plumbing and heating at 82% complete
  • 2nd fix electrical is 19% complete, with plumbing and heating 10% progressed
  • Kitchen units and appliances have been 36% installed so far
  • Doorframes are 40% progressed
  • Skirting and architrave are now 38% complete
  • Bathroom sanitary fittings are 45% complete
  • Wall and floor tiling are 24% progressed
  • Carpet and floor finishes have made great progress
  • Doors and ironmongery are 32% progressed thus far
  • Decorations have been making progress and are 30% complete

At ELEMENT – The Quarter, work has been progressing nicely and a number of tasks have reached completion, including the upper suspended steel floor structure and dire coating to the steel framework.

Tasks making progress include the ground floor slab an underground drainage. In terms of internal fit out, 1st fix electrical is 80% progressed with good progress being made to plaster finishes on walls and ceilings.

Summary of Works Progressed 

  • Steel frame structure is complete
  • Retaining walls and concrete beam foundations are now 80% complete
  • Underground drainage is 98% progressed and approaching completion
  • Construction of the ground floor slab is now 55% complete
  • Upper suspended steel floor structure is 100% complete
  • Fire coating to the steel framework is also complete
  • Structural framework forming the external walls is 93% progressed
  • Scaffolding and mast climber access has achieved 98% progression so far
  • Development to the flat roof covering including balconies is 87% complete
  • Weatherboarding is 87% complete
  • External windows, doors and curtain walling are 78% progressed
  • External wall insulation and render is 65% progressed
  • The Mansafe system is 60% complete
  • Core drilling services and above ground drainage are complete
  • Partition walls installation is ongoing
  • Apartment ceiling installation has reached the halfway mark
  • Plaster finishes to walls and ceilings are 30% progressed
  • 1st fix electrical is 80% progressed with plumbing and heating not far behind
  • 2nd fix works are in progress
  • Kitchen units and appliances have been 15% installed so far
  • Doorframes, skirting and architrave are all underway
  • Bathroom sanitary fittings are 44% complete
  • Wall and floor tiling have commenced
  • Carpet and floor finishes are 18% complete
  • Doors and ironmongery are 14% progressed thus far
  • Decorations have been making progress

During June at ELEMENT – The Quarter, we saw progression in a number of areas including the retaining walls, upper suspended steel floor structure and weatherboarding, to name just a few.

Other activity on site includes the installation of external windows and doors, scaffolding access, fire coating to the steel framework and work on the Mansafe system.

Summary of Works Progressed 

  • Retaining walls and concrete beam foundations are progressing
  • Underground drainage is 95% progressed and approaching completion
  • Construction of the ground floor slab has made significant progress and is halfway to completion
  • Upper suspended steel floor structure is approaching completion
  • Fire coating to the steel framework is underway
  • Work continues to the structural framework forming the external walls
  • Scaffolding and mast climber access has achieved 95% progression so far
  • Development to the flat roof covering including balconies
  • Weatherboarding is 85% complete
  • External windows, doors and curtain walling are 78% progressed
  • External wall insulation and render is 65% progressed
  • The Mansafe system is 48% complete

This month at ELEMENT – The Quarter, the internal stair structure and sub-structure masonry walls have been completed. Also, finalisations are being made to the underground drainage.

Another task nearing completion is the steel frame structure, and finishing touches are being made to the upper suspended steel floor structure. Rapid progress is being made on the flat roof coverings including balconies across the entire site.

Summary of Works Progressed 

  • Retaining walls and concrete beam foundations are 45% complete
  • Commencement of ground floor slab construction
  • Steel frame structure nearing completion
  • Finalisations to underground drainage
  • 96% completion on upper suspended steel floor structure
  • Completion of internal stair structure
  • Sub-structure masonry walls are 100% complete
  • Finishing touches to fire coat steel framework
  • Structural framework forming external walls is 72% developed
  • Scaffolding and mast climber access nearing finalisation
  • Rapid progress on flat roof coverings including balconies
  • Flat roof structure is 88% progressed
  • 75% completion of weatherboarding
  • Over halfway completion of external windows/doors and curtain walling
  • External wall insulation and render now 55% complete
  • Clear development of Mansafe system

At ELEMENT – The Quarter, the internal staircase structure and sub-structure masonry walls have now been completed. A number of other tasks have progressed during this time. 

Activities such as constructing the flat roof structure, underground drainage, retaining walls and concrete beam foundations are all greatly underway and making quick progress.  

Summary of Works Progressed 

  • Internal staircase structure has been completed 
  • Sub-structure and masonry walls complete 
  • Steel frame structure is 2from completion 
  • Underground drainage is 90% complete  
  • Flat roof structure is 85% complete  
  • Scaffolding and mast climber access is nearing completion  
  • Works have begun on external windows, doors and curtain walling  
  • Weatherboarding is 40% complete  
  • Work is halfway complete on the structural framework forming the external walls  
  • Fire coating to the steel framework is 60% complete 
  • The upper suspended steel floor structure is almost completed 
  • Retaining walls and concrete beam foundations are 20% away from completion 

At ELEMENT – The Quarter the metal floor decking to the steel frame is 80% complete as well as steel frame alterations. A number of other tasks have progressed during this time. 

Tasks such as intumescent primer, roof decking, retaining wall, reinforcement and soil vent pipe installation are underway and making quick progress. Orders have been placed for windows which are currently being manufactured, and masonry support will arrive on site early October. 

Summary of Work Progressed 

  • Intumescent primer paint application to steel frame is 55% complete   
  • Metal floor decking to the steel frame is 80% complete 
  • Steel frame alterations have commenced and are 80% complete 
  • Phase 1 of installation of the hoist and mast climbers complete  
  • Steel frame structure and boarding is 20% complete 
  • Roof decking is complete to Phase 1 
  • Retaining wall is 85% complete 
  • Masonry support has been ordered and due to site early October 2021 
  • Windows are being manufactured and are due November 2021 
  • Installation of reinforcement is 50% complete 
  • Mechanical and electrical containment is 10% complete 
  • Soil vent pipe and rain water pipe installation is 10% complete 

Works Anticipated 

  • Phase 1 of installation of the hoist and mast climbers complete.  
  • Concrete floor slabs commencing 
  • Blockwork due to start 1st week of October 
  • Masonry support to arrive on site 
  • Drainage and ground beams to commence October 2021 
  • Roofing package commencing October 2021 
  • Windows to arrive on site in November  
  • Internal room partitions commencing November 2021 
  • External brickwork commencing November 2021  

In this first construction update for ELEMENT – The Quarter, a clean-up was completed on site to ensure that it was ready for permanent works to commence.

The site is now ready and contractors have commenced the intumescent paint and primer, and there are a number of tasks scheduled in for the coming weeks. These include metal floor decking, steel frame alterations and the steel frame structure and boarding.

Summary of Works Progress

  • A clean-up took place to prepare the site for permanent works and to allow for contractors to commence
  • Intumescent paint and primer to steel frame has commenced

Works Anticipated

  • Metal floor decking to the steel frame to commence
  • Commence steel frame alterations
  • Commence the installation of the hoist and mast climbers
  • Steel frame structure and boarding to commence
  • Scaffolding, turnstile and temporary electrics will also commence to facilitate the permanent works

2022

Lift installation has now commenced at ELEMENT – The Quarter, with other internal works racing ahead.

1st and 2nd fix electrical, plumbing and heating works are all making great progress. Carpet and floor finishes are making excellent headway, as well as plaster finishes to walls and ceiling, doorframes, skirting and architrave.

Summary of Works Progressed 

  • Retaining walls and concrete beam foundations are now 85% complete
  • Underground drainage is 99% progressed
  • Scaffolding and mast climber access has achieved 99% progression so far
  • Development to the flat roof covering including balconies is 89% complete
  • Weatherboarding is 87% complete
  • External windows, doors and curtain walling are 80% progressed
  • External wall insulation and render is 75% progressed
  • The Mansafe system is 60% complete
  • The lift has been installed to 40%
  • Partition wall installation is 69% complete
  • Apartment ceiling installation is 50% complete
  • Plaster finishes to walls and ceilings are now 55% progressed
  • 1st fix electrical is 86% progressed with plumbing and heating at 82% complete
  • 2nd fix electrical is 19% complete, with plumbing and heating 10% progressed
  • Kitchen units and appliances have been 36% installed so far
  • Doorframes are 40% progressed
  • Skirting and architrave are now 38% complete
  • Bathroom sanitary fittings are 45% complete
  • Wall and floor tiling are 24% progressed
  • Carpet and floor finishes have made great progress
  • Doors and ironmongery are 32% progressed thus far
  • Decorations have been making progress and are 30% complete

At ELEMENT – The Quarter, work has been progressing nicely and a number of tasks have reached completion, including the upper suspended steel floor structure and dire coating to the steel framework.

Tasks making progress include the ground floor slab an underground drainage. In terms of internal fit out, 1st fix electrical is 80% progressed with good progress being made to plaster finishes on walls and ceilings.

Summary of Works Progressed 

  • Steel frame structure is complete
  • Retaining walls and concrete beam foundations are now 80% complete
  • Underground drainage is 98% progressed and approaching completion
  • Construction of the ground floor slab is now 55% complete
  • Upper suspended steel floor structure is 100% complete
  • Fire coating to the steel framework is also complete
  • Structural framework forming the external walls is 93% progressed
  • Scaffolding and mast climber access has achieved 98% progression so far
  • Development to the flat roof covering including balconies is 87% complete
  • Weatherboarding is 87% complete
  • External windows, doors and curtain walling are 78% progressed
  • External wall insulation and render is 65% progressed
  • The Mansafe system is 60% complete
  • Core drilling services and above ground drainage are complete
  • Partition walls installation is ongoing
  • Apartment ceiling installation has reached the halfway mark
  • Plaster finishes to walls and ceilings are 30% progressed
  • 1st fix electrical is 80% progressed with plumbing and heating not far behind
  • 2nd fix works are in progress
  • Kitchen units and appliances have been 15% installed so far
  • Doorframes, skirting and architrave are all underway
  • Bathroom sanitary fittings are 44% complete
  • Wall and floor tiling have commenced
  • Carpet and floor finishes are 18% complete
  • Doors and ironmongery are 14% progressed thus far
  • Decorations have been making progress

During June at ELEMENT – The Quarter, we saw progression in a number of areas including the retaining walls, upper suspended steel floor structure and weatherboarding, to name just a few.

Other activity on site includes the installation of external windows and doors, scaffolding access, fire coating to the steel framework and work on the Mansafe system.

Summary of Works Progressed 

  • Retaining walls and concrete beam foundations are progressing
  • Underground drainage is 95% progressed and approaching completion
  • Construction of the ground floor slab has made significant progress and is halfway to completion
  • Upper suspended steel floor structure is approaching completion
  • Fire coating to the steel framework is underway
  • Work continues to the structural framework forming the external walls
  • Scaffolding and mast climber access has achieved 95% progression so far
  • Development to the flat roof covering including balconies
  • Weatherboarding is 85% complete
  • External windows, doors and curtain walling are 78% progressed
  • External wall insulation and render is 65% progressed
  • The Mansafe system is 48% complete

This month at ELEMENT – The Quarter, the internal stair structure and sub-structure masonry walls have been completed. Also, finalisations are being made to the underground drainage.

Another task nearing completion is the steel frame structure, and finishing touches are being made to the upper suspended steel floor structure. Rapid progress is being made on the flat roof coverings including balconies across the entire site.

Summary of Works Progressed 

  • Retaining walls and concrete beam foundations are 45% complete
  • Commencement of ground floor slab construction
  • Steel frame structure nearing completion
  • Finalisations to underground drainage
  • 96% completion on upper suspended steel floor structure
  • Completion of internal stair structure
  • Sub-structure masonry walls are 100% complete
  • Finishing touches to fire coat steel framework
  • Structural framework forming external walls is 72% developed
  • Scaffolding and mast climber access nearing finalisation
  • Rapid progress on flat roof coverings including balconies
  • Flat roof structure is 88% progressed
  • 75% completion of weatherboarding
  • Over halfway completion of external windows/doors and curtain walling
  • External wall insulation and render now 55% complete
  • Clear development of Mansafe system

2021

At ELEMENT – The Quarter, the internal staircase structure and sub-structure masonry walls have now been completed. A number of other tasks have progressed during this time. 

Activities such as constructing the flat roof structure, underground drainage, retaining walls and concrete beam foundations are all greatly underway and making quick progress.  

Summary of Works Progressed 

  • Internal staircase structure has been completed 
  • Sub-structure and masonry walls complete 
  • Steel frame structure is 2from completion 
  • Underground drainage is 90% complete  
  • Flat roof structure is 85% complete  
  • Scaffolding and mast climber access is nearing completion  
  • Works have begun on external windows, doors and curtain walling  
  • Weatherboarding is 40% complete  
  • Work is halfway complete on the structural framework forming the external walls  
  • Fire coating to the steel framework is 60% complete 
  • The upper suspended steel floor structure is almost completed 
  • Retaining walls and concrete beam foundations are 20% away from completion 

At ELEMENT – The Quarter the metal floor decking to the steel frame is 80% complete as well as steel frame alterations. A number of other tasks have progressed during this time. 

Tasks such as intumescent primer, roof decking, retaining wall, reinforcement and soil vent pipe installation are underway and making quick progress. Orders have been placed for windows which are currently being manufactured, and masonry support will arrive on site early October. 

Summary of Work Progressed 

  • Intumescent primer paint application to steel frame is 55% complete   
  • Metal floor decking to the steel frame is 80% complete 
  • Steel frame alterations have commenced and are 80% complete 
  • Phase 1 of installation of the hoist and mast climbers complete  
  • Steel frame structure and boarding is 20% complete 
  • Roof decking is complete to Phase 1 
  • Retaining wall is 85% complete 
  • Masonry support has been ordered and due to site early October 2021 
  • Windows are being manufactured and are due November 2021 
  • Installation of reinforcement is 50% complete 
  • Mechanical and electrical containment is 10% complete 
  • Soil vent pipe and rain water pipe installation is 10% complete 

Works Anticipated 

  • Phase 1 of installation of the hoist and mast climbers complete.  
  • Concrete floor slabs commencing 
  • Blockwork due to start 1st week of October 
  • Masonry support to arrive on site 
  • Drainage and ground beams to commence October 2021 
  • Roofing package commencing October 2021 
  • Windows to arrive on site in November  
  • Internal room partitions commencing November 2021 
  • External brickwork commencing November 2021  

In this first construction update for ELEMENT – The Quarter, a clean-up was completed on site to ensure that it was ready for permanent works to commence.

The site is now ready and contractors have commenced the intumescent paint and primer, and there are a number of tasks scheduled in for the coming weeks. These include metal floor decking, steel frame alterations and the steel frame structure and boarding.

Summary of Works Progress

  • A clean-up took place to prepare the site for permanent works and to allow for contractors to commence
  • Intumescent paint and primer to steel frame has commenced

Works Anticipated

  • Metal floor decking to the steel frame to commence
  • Commence steel frame alterations
  • Commence the installation of the hoist and mast climbers
  • Steel frame structure and boarding to commence
  • Scaffolding, turnstile and temporary electrics will also commence to facilitate the permanent works

Future Completed Project Visualizations

Invest in ELEMENT – The Quarter

View Property Details

Refer a Friend to RWinvest

Have you heard about our referral scheme? With our referral scheme, you can be rewarded by simply recommending a fellow investor to RWinvest.

Each time you refer someone to our properties, and they go on to make a sale, you’ll earn £500. It’s one of the easiest ways to generate a quick cash boost on top of your lucrative investment earnings!

If you have a friend or family member who’s thinking of buying an investment property, and you’re happy with the service you experienced with us, get in touch with us today to find out how to get involved with our referral scheme.

Exciting New Launch
Liverpool Prices from £94,950

Completed and Tenanted Student Accommodation

Central Liverpool Location

Desirable Manchester Location

Embankment Exchange

80% Units Sold

Manchester Prices from £225,950

6% Projected Rental Returns

Up to 34% Below Local Comparable

Invest From £50,000

The Hive

Creating a Buzz in the Luton Market

Luton Prices from £194,950

5% Rental Returns 

75% Sold Out - Units Selling Fast

Welcome, visitor!