ELEMENT – The Quarter Construction Updates

The Latest on ELEMENT - The Quarter

ELEMENT – The Quarter is the first eco development in Liverpool, brought to the market by RWinvest and Nexus Residential. This development welcomes both postgraduate students and professionals into luxury accommodation in Liverpool with amazing onsite facilities. Here are all of the latest ELEMENT – The Quarter construction updates:

  • Sub-structure masonry walls are 100% complete
  • Commencement of ground floor slab construction
  • Completion of internal stair structure

2022

2021

This month at ELEMENT – The Quarter, the internal stair structure and sub-structure masonry walls have been completed. Also, finalisations are being made to the underground drainage.

Another task nearing completion is the steel frame structure, and finishing touches are being made to the upper suspended steel floor structure. Rapid progress is being made on the flat roof coverings including balconies across the entire site.

Summary of Works Progressed 

  • Retaining walls and concrete beam foundations are 45% complete
  • Commencement of ground floor slab construction
  • Steel frame structure nearing completion
  • Finalisations to underground drainage
  • 96% completion on upper suspended steel floor structure
  • Completion of internal stair structure
  • Sub-structure masonry walls are 100% complete
  • Finishing touches to fire coat steel framework
  • Structural framework forming external walls is 72% developed
  • Scaffolding and mast climber access nearing finalisation
  • Rapid progress on flat roof coverings including balconies
  • Flat roof structure is 88% progressed
  • 75% completion of weatherboarding
  • Over halfway completion of external windows/doors and curtain walling
  • External wall insulation and render now 55% complete
  • Clear development of Mansafe system

At ELEMENT – The Quarter, the internal staircase structure and sub-structure masonry walls have now been completed. A number of other tasks have progressed during this time. 

Activities such as constructing the flat roof structure, underground drainage, retaining walls and concrete beam foundations are all greatly underway and making quick progress.  

Summary of Works Progressed 

  • Internal staircase structure has been completed 
  • Sub-structure and masonry walls complete 
  • Steel frame structure is 2from completion 
  • Underground drainage is 90% complete  
  • Flat roof structure is 85% complete  
  • Scaffolding and mast climber access is nearing completion  
  • Works have begun on external windows, doors and curtain walling  
  • Weatherboarding is 40% complete  
  • Work is halfway complete on the structural framework forming the external walls  
  • Fire coating to the steel framework is 60% complete 
  • The upper suspended steel floor structure is almost completed 
  • Retaining walls and concrete beam foundations are 20% away from completion 

At ELEMENT – The Quarter the metal floor decking to the steel frame is 80% complete as well as steel frame alterations. A number of other tasks have progressed during this time. 

Tasks such as intumescent primer, roof decking, retaining wall, reinforcement and soil vent pipe installation are underway and making quick progress. Orders have been placed for windows which are currently being manufactured, and masonry support will arrive on site early October. 

Summary of Work Progressed 

  • Intumescent primer paint application to steel frame is 55% complete   
  • Metal floor decking to the steel frame is 80% complete 
  • Steel frame alterations have commenced and are 80% complete 
  • Phase 1 of installation of the hoist and mast climbers complete  
  • Steel frame structure and boarding is 20% complete 
  • Roof decking is complete to Phase 1 
  • Retaining wall is 85% complete 
  • Masonry support has been ordered and due to site early October 2021 
  • Windows are being manufactured and are due November 2021 
  • Installation of reinforcement is 50% complete 
  • Mechanical and electrical containment is 10% complete 
  • Soil vent pipe and rain water pipe installation is 10% complete 

Works Anticipated 

  • Phase 1 of installation of the hoist and mast climbers complete.  
  • Concrete floor slabs commencing 
  • Blockwork due to start 1st week of October 
  • Masonry support to arrive on site 
  • Drainage and ground beams to commence October 2021 
  • Roofing package commencing October 2021 
  • Windows to arrive on site in November  
  • Internal room partitions commencing November 2021 
  • External brickwork commencing November 2021  

In this first construction update for ELEMENT – The Quarter, a clean-up was completed on site to ensure that it was ready for permanent works to commence.

The site is now ready and contractors have commenced the intumescent paint and primer, and there are a number of tasks scheduled in for the coming weeks. These include metal floor decking, steel frame alterations and the steel frame structure and boarding.

Summary of Works Progress

  • A clean-up took place to prepare the site for permanent works and to allow for contractors to commence
  • Intumescent paint and primer to steel frame has commenced

Works Anticipated

  • Metal floor decking to the steel frame to commence
  • Commence steel frame alterations
  • Commence the installation of the hoist and mast climbers
  • Steel frame structure and boarding to commence
  • Scaffolding, turnstile and temporary electrics will also commence to facilitate the permanent works

2022

This month at ELEMENT – The Quarter, the internal stair structure and sub-structure masonry walls have been completed. Also, finalisations are being made to the underground drainage.

Another task nearing completion is the steel frame structure, and finishing touches are being made to the upper suspended steel floor structure. Rapid progress is being made on the flat roof coverings including balconies across the entire site.

Summary of Works Progressed 

  • Retaining walls and concrete beam foundations are 45% complete
  • Commencement of ground floor slab construction
  • Steel frame structure nearing completion
  • Finalisations to underground drainage
  • 96% completion on upper suspended steel floor structure
  • Completion of internal stair structure
  • Sub-structure masonry walls are 100% complete
  • Finishing touches to fire coat steel framework
  • Structural framework forming external walls is 72% developed
  • Scaffolding and mast climber access nearing finalisation
  • Rapid progress on flat roof coverings including balconies
  • Flat roof structure is 88% progressed
  • 75% completion of weatherboarding
  • Over halfway completion of external windows/doors and curtain walling
  • External wall insulation and render now 55% complete
  • Clear development of Mansafe system

2021

At ELEMENT – The Quarter, the internal staircase structure and sub-structure masonry walls have now been completed. A number of other tasks have progressed during this time. 

Activities such as constructing the flat roof structure, underground drainage, retaining walls and concrete beam foundations are all greatly underway and making quick progress.  

Summary of Works Progressed 

  • Internal staircase structure has been completed 
  • Sub-structure and masonry walls complete 
  • Steel frame structure is 2from completion 
  • Underground drainage is 90% complete  
  • Flat roof structure is 85% complete  
  • Scaffolding and mast climber access is nearing completion  
  • Works have begun on external windows, doors and curtain walling  
  • Weatherboarding is 40% complete  
  • Work is halfway complete on the structural framework forming the external walls  
  • Fire coating to the steel framework is 60% complete 
  • The upper suspended steel floor structure is almost completed 
  • Retaining walls and concrete beam foundations are 20% away from completion 

At ELEMENT – The Quarter the metal floor decking to the steel frame is 80% complete as well as steel frame alterations. A number of other tasks have progressed during this time. 

Tasks such as intumescent primer, roof decking, retaining wall, reinforcement and soil vent pipe installation are underway and making quick progress. Orders have been placed for windows which are currently being manufactured, and masonry support will arrive on site early October. 

Summary of Work Progressed 

  • Intumescent primer paint application to steel frame is 55% complete   
  • Metal floor decking to the steel frame is 80% complete 
  • Steel frame alterations have commenced and are 80% complete 
  • Phase 1 of installation of the hoist and mast climbers complete  
  • Steel frame structure and boarding is 20% complete 
  • Roof decking is complete to Phase 1 
  • Retaining wall is 85% complete 
  • Masonry support has been ordered and due to site early October 2021 
  • Windows are being manufactured and are due November 2021 
  • Installation of reinforcement is 50% complete 
  • Mechanical and electrical containment is 10% complete 
  • Soil vent pipe and rain water pipe installation is 10% complete 

Works Anticipated 

  • Phase 1 of installation of the hoist and mast climbers complete.  
  • Concrete floor slabs commencing 
  • Blockwork due to start 1st week of October 
  • Masonry support to arrive on site 
  • Drainage and ground beams to commence October 2021 
  • Roofing package commencing October 2021 
  • Windows to arrive on site in November  
  • Internal room partitions commencing November 2021 
  • External brickwork commencing November 2021  

In this first construction update for ELEMENT – The Quarter, a clean-up was completed on site to ensure that it was ready for permanent works to commence.

The site is now ready and contractors have commenced the intumescent paint and primer, and there are a number of tasks scheduled in for the coming weeks. These include metal floor decking, steel frame alterations and the steel frame structure and boarding.

Summary of Works Progress

  • A clean-up took place to prepare the site for permanent works and to allow for contractors to commence
  • Intumescent paint and primer to steel frame has commenced

Works Anticipated

  • Metal floor decking to the steel frame to commence
  • Commence steel frame alterations
  • Commence the installation of the hoist and mast climbers
  • Steel frame structure and boarding to commence
  • Scaffolding, turnstile and temporary electrics will also commence to facilitate the permanent works

Future Completed Project Visualizations

Invest in ELEMENT – The Quarter

View Property Details

Refer a Friend to RWinvest

Have you heard about our referral scheme? With our referral scheme, you can be rewarded by simply recommending a fellow investor to RWinvest.

Each time you refer someone to our properties, and they go on to make a sale, you’ll earn £500. It’s one of the easiest ways to generate a quick cash boost on top of your lucrative investment earnings!

If you have a friend or family member who’s thinking of buying an investment property, and you’re happy with the service you experienced with us, get in touch with us today to find out how to get involved with our referral scheme.

Liverpool L1 City Centre Postcode

The Mill

Invest From £39,950

Liverpool Prices from £139,950

Assured 6% NET Rental Return

Grade 2 Listed Building

Exclusive Payment Structure

One Park Lane

Exclusive Liverpool Investment

Liverpool Prices from £129,950

6% Assured Net Rental Return

16 Storey Skyscraper

Invest With £29,990

Heaps Mill

Exclusive RWinvest Opportunity

Liverpool Prices from £124,950

7% Assured Net Rental Return

Deposits From as Little as 15%