Merchant’s Wharf Construction Updates

The Latest on Merchant’s Wharf

Merchant’s Wharf is the first development in Manchester by Legacie Developments. RWinvest has worked with Legacie on many of its sites throughout Liverpool, which were completed and tenanted in record time. This is an exciting time in the Manchester property market and you can see all of the latest Merchant’s Wharf construction updates here on this page.

Current Progress

  • Removal of Underground Obstructions
  • Semi-Permanent Site Acommodation Now Installed
  • Earthworks to Prepare for Piling Mat Installation

2021

At Merchant’s Wharf, additional site investigation works have been required to ascertain any further underground obstructions which are now being removed. The piling mat installation is currently underway.

Other works include earthworks to prepare for installation of the piling mat to the full site. Excavated materials have also been crushed and recycled to use within the piling mat.

Summary of Works Progressed

  • Additional site investigation works have been required to ascertain any obstructions underground prior to the CFA piling commencing
  • The semi-permanent site accommodation has now been installed and will be position until project completion
  • Further obstructions underwent removal works prior to CFA piling commencing
  • Crushing and recycling excavated materials for use within the piling mat to carry the weight of the piling rig
  • Earthworks to prepare for the installation of the piling mat to the full site
  • Piling mat installation works commenced and currently ongoing

May 2021

In the first construction update for Merchant’s Wharf, we can confirm that site set up is ongoing, with stage 2 site investigation works complete and site demolition commenced.

The internal soft strip demolition has already been completed, with the main demolition commenced and due to take around 6 weeks the complete. This includes the removal of the roof.

 

Summary of Works Progressed

  • Site set up is ongoing, including welfare and site perimeter fencing
  • Stage 2 site investigation works are complete
  • Proof digging and trial trenches completed
  • Site demolition has commenced including internal soft strip and main demolition
  • Internal soft strip completed
  • Removal of the roof commenced
  • Surveyor has been appointed for the party wall and discussions are ongoing between all parties

 

Works Scheduled

  • Progression of the full demolition which will complete after approximately 6 weeks

2021

At Merchant’s Wharf, additional site investigation works have been required to ascertain any further underground obstructions which are now being removed. The piling mat installation is currently underway.

Other works include earthworks to prepare for installation of the piling mat to the full site. Excavated materials have also been crushed and recycled to use within the piling mat.

Summary of Works Progressed

  • Additional site investigation works have been required to ascertain any obstructions underground prior to the CFA piling commencing
  • The semi-permanent site accommodation has now been installed and will be position until project completion
  • Further obstructions underwent removal works prior to CFA piling commencing
  • Crushing and recycling excavated materials for use within the piling mat to carry the weight of the piling rig
  • Earthworks to prepare for the installation of the piling mat to the full site
  • Piling mat installation works commenced and currently ongoing

May 2021

In the first construction update for Merchant’s Wharf, we can confirm that site set up is ongoing, with stage 2 site investigation works complete and site demolition commenced.

The internal soft strip demolition has already been completed, with the main demolition commenced and due to take around 6 weeks the complete. This includes the removal of the roof.

 

Summary of Works Progressed

  • Site set up is ongoing, including welfare and site perimeter fencing
  • Stage 2 site investigation works are complete
  • Proof digging and trial trenches completed
  • Site demolition has commenced including internal soft strip and main demolition
  • Internal soft strip completed
  • Removal of the roof commenced
  • Surveyor has been appointed for the party wall and discussions are ongoing between all parties

 

Works Scheduled

  • Progression of the full demolition which will complete after approximately 6 weeks

Future Completed Project Visualizations

parallax-image

Invest in Merchant’s Wharf

View Property Details

Refer a Friend to RWinvest

Have you heard about our referral scheme? With our referral scheme, you can be rewarded by simply recommending a fellow investor to RWinvest.

Each time you refer someone to our properties, and they go on to make a sale, you’ll earn £500. It’s one of the easiest ways to generate a quick cash boost on top of your lucrative investment earnings!

If you have a friend or family member who’s thinking of buying an investment property, and you’re happy with the service you experienced with us, get in touch with us today to find out how to get involved with our referral scheme.

3 Units Remaining

The Summit

Stylish Baltic Triangle Living

Liverpool Prices from £139,950

Assured 7% NET Rental Yields

15-20% Below Market Value

Invest From £35,000

ELEMENT - The Quarter

North West's First Eco-Development

Liverpool Prices from £74,950

8% NET Rental Return

300m Away From New £1bn Royal Hospital

10% Deposit

Off Market Manchester Apartments

Premium Residential Investment

Manchester Prices from £219,112

5.5% NET Rental Return

10% Deposit Required