See below for all of the Parliament Square construction updates, documenting how this promising Baltic Triangle development is flourishing through its consistent progress.

Current Progress

  • Partition walls are 93% progressed
  • Lift installation 50% complete
  • Second fix 59% progressed

At Block C, the tower’s external works have progressed significantly with the above ground drainage now 90% complete. A number of internal tasks are also progressing well.

All first fix works are 90% progressed and bathroom and sanitary fittings have made progress to 82% completion. Decorations and second fix works are 59% complete.

Summary of Works Progressed

  • The flat roof covering including balconies is 20% progressed
  • External windows, doors and curtain walling is 75% complete
  • External wall cladding and insulation is 65% progressed so far
  • Above ground drainage is now 90% complete
  • Riser installation is 5% complete
  • Lift installation is 50% complete
  • Partition walls are 93% progressed
  • Apartment ceilings have progressed well and are now 93% complete
  • Plaster finishes are now 82% progressed
  • All first fix works are 90% progressed
  • Kitchen units and appliances are being installed and are 64% complete
  • Doorframes are being installed and at 80% progression so far
  • Skirting and architrave is 74% progressed
  • Bathroom sanitary fittings are 82% complete
  • Wall and floor tiling is progressing well and at 80% completion
  • Carpet and floor finishes are 70% complete
  • Decorations and second fix works are 59% complete
  • Doors and ironmongery are 30% complete

The tower’s structural framework forming the external walls is now complete as well as weatherboarding, scaffolding and mast climbers and the flat roof structure.

Other tasks progressing well internally include apartment ceilings, wall and floor tiling, bathroom sanitary fittings and both first and second fix electrical, mechanical and plumbing works. Kitchen units and appliances are now installed to 50%.

Summary of Works Progressed

  • Structural framework forming the external walls is complete
  • Scaffolding and mast climber access is 100% complete
  • The flat roof structure is also complete
  • Weatherboarding has completed
  • The flat roof covering has progressed
  • External windows, doors and curtain walling is 75% complete
  • External wall cladding and insulation is 45% progressed so far
  • Above ground drainage is now 83% complete
  • Partition walls are 85% progressed
  • Apartment ceilings have progressed well and are now 77% complete
  • Plaster finishes are now 72% progressed
  • All first fix works are ongoing
  • Kitchen units and appliances are being installed and are halfway complete
  • Doorframes are being installed
  • Skirting and architrave is 28% progressed
  • Bathroom sanitary fittings are 41% complete
  • Wall and floor tiling is progressing well
  • Carpet and floor finishes plus decorations are both 40% complete
  • Second fix works are 35% complete

February 2021

Parliament Square Block C is progressing in every possible way.

So much has happened at Block C, Parliament Square. The flat roof structure is nearly complete, first fix works are progressing nicely, and wall and floor tiling have made an excellent start. Carpet and floor finishes are being installed and kitchen units and appliances are underway.

 

Summary of Works Progressed

  • The structural framework forming external walls is 71% complete.
  • Scaffolding and mast climber access are 80% complete.
  • The flat roof structure is 95% complete.
  • Flat roof covering including balconies has progressed by 15%.
  • Weatherboarding Is 63% complete.
  • External windows, doors and curtain walling is 69% progressed.
  • Brickwork and insulation to elevations has commenced and 2% progressed so far.
  • External wall cladding is now also underway and 2% progressed.
  • The riser installation is 5% complete.
  • Lift installation is 15% progressed.
  • Above ground drainage has been ongoing and is 60% complete.
  • Partition walls have been installed to 67%.
  • Apartment ceilings have been installed to 56%.
  • Plaster finishes to walls and ceilings are halfway complete.
  • First fix electrical is 58% progressed and first fix plumbing and heating is 65% progressed.
  • Kitchen units and appliances are 14% completes so far.
  • Door frames are commenced and 5% progressed.
  • Skirting and architrave are 7% complete.
  • Bathroom sanitary fittings are 15% progressed.
  • Wall and floor tiling have progressed to 19% and carpet and floor finishes are 13% complete.
  • Decorations are now 12% complete in Block C.

November 2020

Block C floor slab, concrete frame structure and staircase structure are now all 70% complete.

Weatherboarding has commenced and can be seen working its way up the tower, as well as window installation and external walls taking shape.

Summary of Works Progressed -Block C

  • Underground drainage 100% complete
  • Floor slab construction to all floors is 70% complete
  • Concrete frame structure is 70% progressed
  • Internal staircase structure also 70% progressed
  • Structural framework forming external walls is 35% underway
  • Weatherboarding commenced and 20% progressed
  • Window installation ongoing
  • Mechanical services are being installed

August 2020

Several tasks have been completed at Parliament Square Block C, including ground infill, site levelling, retaining walls and concrete beam foundations.

While a number of activities have been completed, excellent progress has been made to the concrete frame structure and the concrete pour to the upper suspended floor structure.

Summary of Works Progressed

  • Site compound and temporary supplies are 100% complete.
  • Ground infill and site levelling 100% complete.
  • Piling foundations completed.
  • Retaining walls and concrete beam foundations 100% complete.
  • Underground drainage 90% complete.
  • Floor slab construction 10% complete.
  • Lift and staircase core concrete structure are 100% complete.
  • Concrete frame structure 34% complete.
  • Concrete pour and upper suspended floor structure 34% complete.
  • Internal staircase structure 12% complete.

May 2020

Block C has seen significant construction progress over the last few weeks, especially with the lift shaft, stairwell and concrete foundations.

Other progress throughout the development includes substantial work on the basement, including retaining walls and foundations. Ground infill and levelling is now approaching completion.

Summary of Works Progressed

  • Site compound and supplies 90% complete.
  • Steel reinforcement concrete slab, column structures and reinforcement starter bars 35% progressed.
  • Basement slab and concrete columns formed, column pad foundations in.
  • Floor slab construction commenced 30% and concrete foundations poured. Podium slabs installed under construction block.
  • Excavations and cage reinforcement for concrete foundations. Concrete pad foundations and cages installed.
  • Further progress to ground infill and levelling which are 98% complete.
  • Retaining walls and concrete beam foundations progressed 60%.
  • Retaining walls and foundations to the basement car park.
  • Progress to basement stairwell structure.
  • Lift shaft and stairwell under construction.
  • Hoist instalment at basement level.
  • Easi-edge handrail system installed.

February 2020

Ground infill is 90% progressed at Parliament Square with piling foundations 100% complete.

The progress at Parliament Square during this construction period has seen the formation of concrete retaining walls and steelwork has been put in place ready for the construction of columns.

Summary of Works Progressed

  • The site compound and temporary supplies are 50% complete with site floodlights and a site washdown cleaning facility now installed.
  • Ground infill and site levelling is nearly completed at 90%.
  • Piling foundations are 100% complete with piled retaining concrete walls formed.
  • Concrete retaining walls have progressed by 10% and service ducts have been formed in the walls. The retaining walls have been waterproofed.
  • Concrete beam foundations have commenced and are 10% complete.
  • Steelwork has been put in place for column construction and concrete pads have been formed to support these columns.
  • The crane pad is under construction.
  • Excavation to the sandstone car park base.

 

Works Scheduled

  • Construction of columns.

November 2019

With demolition complete, construction has begun at Parliament Square in Liverpool and work is progressing nicely.

There has been significant construction activity to the sub-structure and super-structure during the latest period, including the ground being infilled and levelled, and the progress of pilings and concrete foundations.

 

Summary of Works Progressed

• Demolition is now complete.
• Site clearance is 100% complete.
• Trial pit areas were marked out and dug as part of ground investigations.
• The site compound and temporary supplies have progressed by 50%.
• The ground is being infilled and levelled which has made great progress of 80%.
• Pilings and the concrete foundations have progressed by 60%. The pile foundation has formed the retaining wall.
• Reinforced steel cages are on site and prepared.

 

Works Scheduled

• Reinforced steel cages ready to be driven into the pile holes.

August 2019

Parliament Square’s full construction schedule has been confirmed.

In the most recent update from the developer of Parliament Square, we have been informed that the team are now being set up on-site in preparation to commence construction works.

 

Summary of Works Progressed

• Excavation works completed.
• A full schedule has been put in place.

 

Works Scheduled

• Commence the bulk dig involving removing, adding and moving rock and soil around the site to achieve a suitable height for construction.
• Piling with the contiguous walls, a deep foundation part of the groundworks to help form a watertight retaining wall.
• Commence the main groundworks package.
• Concrete frame installation.

May 2019

Work has begun at Parliament Square in Liverpool, with the first construction update showing that the hoarding has been successfully erected around the site.

The area is undergoing various preparations. Extensive site investigations entailing numerous collections of data and reports have now been completed. Excavation has commenced which involves works to the earth, such as trenching and tunnelling underground.

 

Summary of Works Progressed

• The hoarding has been 100% erected.
• 100% of site investigation works have been completed.
• Excavation works have commenced.

 

Works Scheduled

• Completion of excavation works.
• Sewage and drainage work to commence.

2021

At Block C, the tower’s external works have progressed significantly with the above ground drainage now 90% complete. A number of internal tasks are also progressing well.

All first fix works are 90% progressed and bathroom and sanitary fittings have made progress to 82% completion. Decorations and second fix works are 59% complete.

Summary of Works Progressed

  • The flat roof covering including balconies is 20% progressed
  • External windows, doors and curtain walling is 75% complete
  • External wall cladding and insulation is 65% progressed so far
  • Above ground drainage is now 90% complete
  • Riser installation is 5% complete
  • Lift installation is 50% complete
  • Partition walls are 93% progressed
  • Apartment ceilings have progressed well and are now 93% complete
  • Plaster finishes are now 82% progressed
  • All first fix works are 90% progressed
  • Kitchen units and appliances are being installed and are 64% complete
  • Doorframes are being installed and at 80% progression so far
  • Skirting and architrave is 74% progressed
  • Bathroom sanitary fittings are 82% complete
  • Wall and floor tiling is progressing well and at 80% completion
  • Carpet and floor finishes are 70% complete
  • Decorations and second fix works are 59% complete
  • Doors and ironmongery are 30% complete

The tower’s structural framework forming the external walls is now complete as well as weatherboarding, scaffolding and mast climbers and the flat roof structure.

Other tasks progressing well internally include apartment ceilings, wall and floor tiling, bathroom sanitary fittings and both first and second fix electrical, mechanical and plumbing works. Kitchen units and appliances are now installed to 50%.

Summary of Works Progressed

  • Structural framework forming the external walls is complete
  • Scaffolding and mast climber access is 100% complete
  • The flat roof structure is also complete
  • Weatherboarding has completed
  • The flat roof covering has progressed
  • External windows, doors and curtain walling is 75% complete
  • External wall cladding and insulation is 45% progressed so far
  • Above ground drainage is now 83% complete
  • Partition walls are 85% progressed
  • Apartment ceilings have progressed well and are now 77% complete
  • Plaster finishes are now 72% progressed
  • All first fix works are ongoing
  • Kitchen units and appliances are being installed and are halfway complete
  • Doorframes are being installed
  • Skirting and architrave is 28% progressed
  • Bathroom sanitary fittings are 41% complete
  • Wall and floor tiling is progressing well
  • Carpet and floor finishes plus decorations are both 40% complete
  • Second fix works are 35% complete

February 2021

Parliament Square Block C is progressing in every possible way.

So much has happened at Block C, Parliament Square. The flat roof structure is nearly complete, first fix works are progressing nicely, and wall and floor tiling have made an excellent start. Carpet and floor finishes are being installed and kitchen units and appliances are underway.

 

Summary of Works Progressed

  • The structural framework forming external walls is 71% complete.
  • Scaffolding and mast climber access are 80% complete.
  • The flat roof structure is 95% complete.
  • Flat roof covering including balconies has progressed by 15%.
  • Weatherboarding Is 63% complete.
  • External windows, doors and curtain walling is 69% progressed.
  • Brickwork and insulation to elevations has commenced and 2% progressed so far.
  • External wall cladding is now also underway and 2% progressed.
  • The riser installation is 5% complete.
  • Lift installation is 15% progressed.
  • Above ground drainage has been ongoing and is 60% complete.
  • Partition walls have been installed to 67%.
  • Apartment ceilings have been installed to 56%.
  • Plaster finishes to walls and ceilings are halfway complete.
  • First fix electrical is 58% progressed and first fix plumbing and heating is 65% progressed.
  • Kitchen units and appliances are 14% completes so far.
  • Door frames are commenced and 5% progressed.
  • Skirting and architrave are 7% complete.
  • Bathroom sanitary fittings are 15% progressed.
  • Wall and floor tiling have progressed to 19% and carpet and floor finishes are 13% complete.
  • Decorations are now 12% complete in Block C.

2020

November 2020

Block C floor slab, concrete frame structure and staircase structure are now all 70% complete.

Weatherboarding has commenced and can be seen working its way up the tower, as well as window installation and external walls taking shape.

Summary of Works Progressed -Block C

  • Underground drainage 100% complete
  • Floor slab construction to all floors is 70% complete
  • Concrete frame structure is 70% progressed
  • Internal staircase structure also 70% progressed
  • Structural framework forming external walls is 35% underway
  • Weatherboarding commenced and 20% progressed
  • Window installation ongoing
  • Mechanical services are being installed

August 2020

Several tasks have been completed at Parliament Square Block C, including ground infill, site levelling, retaining walls and concrete beam foundations.

While a number of activities have been completed, excellent progress has been made to the concrete frame structure and the concrete pour to the upper suspended floor structure.

Summary of Works Progressed

  • Site compound and temporary supplies are 100% complete.
  • Ground infill and site levelling 100% complete.
  • Piling foundations completed.
  • Retaining walls and concrete beam foundations 100% complete.
  • Underground drainage 90% complete.
  • Floor slab construction 10% complete.
  • Lift and staircase core concrete structure are 100% complete.
  • Concrete frame structure 34% complete.
  • Concrete pour and upper suspended floor structure 34% complete.
  • Internal staircase structure 12% complete.

May 2020

Block C has seen significant construction progress over the last few weeks, especially with the lift shaft, stairwell and concrete foundations.

Other progress throughout the development includes substantial work on the basement, including retaining walls and foundations. Ground infill and levelling is now approaching completion.

Summary of Works Progressed

  • Site compound and supplies 90% complete.
  • Steel reinforcement concrete slab, column structures and reinforcement starter bars 35% progressed.
  • Basement slab and concrete columns formed, column pad foundations in.
  • Floor slab construction commenced 30% and concrete foundations poured. Podium slabs installed under construction block.
  • Excavations and cage reinforcement for concrete foundations. Concrete pad foundations and cages installed.
  • Further progress to ground infill and levelling which are 98% complete.
  • Retaining walls and concrete beam foundations progressed 60%.
  • Retaining walls and foundations to the basement car park.
  • Progress to basement stairwell structure.
  • Lift shaft and stairwell under construction.
  • Hoist instalment at basement level.
  • Easi-edge handrail system installed.

February 2020

Ground infill is 90% progressed at Parliament Square with piling foundations 100% complete.

The progress at Parliament Square during this construction period has seen the formation of concrete retaining walls and steelwork has been put in place ready for the construction of columns.

Summary of Works Progressed

  • The site compound and temporary supplies are 50% complete with site floodlights and a site washdown cleaning facility now installed.
  • Ground infill and site levelling is nearly completed at 90%.
  • Piling foundations are 100% complete with piled retaining concrete walls formed.
  • Concrete retaining walls have progressed by 10% and service ducts have been formed in the walls. The retaining walls have been waterproofed.
  • Concrete beam foundations have commenced and are 10% complete.
  • Steelwork has been put in place for column construction and concrete pads have been formed to support these columns.
  • The crane pad is under construction.
  • Excavation to the sandstone car park base.

 

Works Scheduled

  • Construction of columns.

2019

November 2019

With demolition complete, construction has begun at Parliament Square in Liverpool and work is progressing nicely.

There has been significant construction activity to the sub-structure and super-structure during the latest period, including the ground being infilled and levelled, and the progress of pilings and concrete foundations.

 

Summary of Works Progressed

• Demolition is now complete.
• Site clearance is 100% complete.
• Trial pit areas were marked out and dug as part of ground investigations.
• The site compound and temporary supplies have progressed by 50%.
• The ground is being infilled and levelled which has made great progress of 80%.
• Pilings and the concrete foundations have progressed by 60%. The pile foundation has formed the retaining wall.
• Reinforced steel cages are on site and prepared.

 

Works Scheduled

• Reinforced steel cages ready to be driven into the pile holes.

August 2019

Parliament Square’s full construction schedule has been confirmed.

In the most recent update from the developer of Parliament Square, we have been informed that the team are now being set up on-site in preparation to commence construction works.

 

Summary of Works Progressed

• Excavation works completed.
• A full schedule has been put in place.

 

Works Scheduled

• Commence the bulk dig involving removing, adding and moving rock and soil around the site to achieve a suitable height for construction.
• Piling with the contiguous walls, a deep foundation part of the groundworks to help form a watertight retaining wall.
• Commence the main groundworks package.
• Concrete frame installation.

May 2019

Work has begun at Parliament Square in Liverpool, with the first construction update showing that the hoarding has been successfully erected around the site.

The area is undergoing various preparations. Extensive site investigations entailing numerous collections of data and reports have now been completed. Excavation has commenced which involves works to the earth, such as trenching and tunnelling underground.

 

Summary of Works Progressed

• The hoarding has been 100% erected.
• 100% of site investigation works have been completed.
• Excavation works have commenced.

 

Works Scheduled

• Completion of excavation works.
• Sewage and drainage work to commence.

Future Completed Project Visualizations

parallax-image

Invest in Parliament Square The Tower

View Property Details

Refer a Friend to RWinvest

Have you heard about our referral scheme? With our referral scheme, you can be rewarded by simply recommending a fellow investor to RWinvest.

Each time you refer someone to our properties, and they go on to make a sale, you’ll earn £500. It’s one of the easiest ways to generate a quick cash boost on top of your lucrative investment earnings!

If you have a friend or family member who’s thinking of buying an investment property, and you’re happy with the service you experienced with us, get in touch with us today to find out how to get involved with our referral scheme.

3 Units Remaining

The Summit

Stylish Baltic Triangle Living

Liverpool Prices from £139,950

Assured 7% NET Rental Yields

15-20% Below Market Value

Invest From £35,000

ELEMENT - The Quarter

North West's First Eco-Development

Liverpool Prices from £74,950

8% NET Rental Return

300m Away From New £1bn Royal Hospital

10% Deposit

Off Market Manchester Apartments

Premium Residential Investment

Manchester Prices from £219,112

5.5% NET Rental Return

10% Deposit Required