Poets Place Construction Updates

The Latest on Poets Place

Seeking to offer luxury, modern apartments within walking distance of Liverpool’s Knowledge Quarter and Business District, this is a development that will show major promise as it develops in the coming months. Check back on this page for all of the latest Poets Place construction updates as they happen.

Current Progress

  • Internal Works Complete
  • External Works Complete
  • Testing and Commissioning 50% Complete

September 2021

All physical building work at Poet’s Place is now complete.

Testing and commissioning is underway and is 50% complete at this time.

Summary of Works Progressed

· All internal works have now been completed

· Work to the exterior of the building is completed

· Testing and commissioning 50% complete

Works Anticipated

· Complete testing and commissioning

· Official sign off

· Tenants to move in

May 2021

Progress has been exceptional at Poet’s Place and the site is now nearing completion.

Window pods, cladding and lift installation are just some of the tasks completed last month. Many of the apartments are now complete and undergoing snagging, with external works also nearing completion. Many of the remaining tasks will be fully complete shortly.

Summary of Works Progressed

  • Project and substation awaiting energisation
  • External cladding and window pods now completed
  • Lift installation now complete, subject to commissioning
  • Juliet balconies progressing well
  • Internal operations progressing as per the programme, with fit out works commenced for all internal trades
  • Partitions, tiling, flooring and painting all making good progress
  • 1st, 2nd and 3rd floor apartments complete and locked off with final snagging process underway
  • External works nearing completion

Works Anticipated

  • Complete internal fit out to apartments and communal areas
  • Complete decoration elements to apartments and communal areas
  • Complete final fix to apartments and communal areas
  • Complete external works
  • Complete the main internal parts of the development
  • Snagging throughout the building
  • Testing and commissioning

February 2021

Great progress has been maintained at Poet’s Place.

During this period, substation works have commenced alongside works for incoming utilities. Other areas have progressed such as cladding, brickwork and internal operations. Fit out for all internal trades is underway and the 1st floor units are now complete, subject to snagging.

Summary of Works Progressed

  • Substation works have now commenced.
  • Works for incoming utilities have commenced.
  • External cladding to upper floors has progressed well.
  • Brickwork has been progressed to all external elevations.
  • Mechanical and electrical 1st fix works have significantly progressed, with 2nd fix works progressed on early floors.
  • Internal operations are making progress as per the programme, with fit out works commenced for all internal trades.
  • Partitions, tiling, flooring, and painting are all well underway.
  • 1st floor apartments are now complete.
  • Snagging process underway on 1st floor units.

Works Anticipated

  • Progression of the superstructure brickwork and cladding.
  • Construction of the substation.
  • Progression to the internal fit out to apartments and communal areas.
  • Progression of the decoration elements to apartments and communal areas.
  • Completion of the 1st fix and progression of the 2nd fix mechanical and electrical works to apartments and communal areas.
  • Progression of the Juliet balconies.
  • Completion of the stair walls.
  • Second floor apartment completed and snagged.

November 2020

Poet’s Place is making visible progress inside and out.

The external elevation brickwork has made great progress to all elevations, as well as the cladding. Inside the development, internal fit out works have commenced and 1st and 2nd fix mechanical and electrical are now well underway.

Summary of Works Progressed

  • External elevation brickwork progressed to all elevations and external works overall are 40% complete
  • External cladding to upper floor commenced
  • Mechanical and electrical 1st fix works significantly progressed and 40% complete overall
  • Mechanical and electrical 2nd fix commenced on early floors
  • Internal fit out works commenced for all internal trades, with partitions, tiling, flooring and painting all making good progress throughout the building up to the 7th floor
  • 1st floor apartments are now significantly complete
  • Lightning protection 80% complete

Works Scheduled

  • Progression of the superstructure brickwork
  • Completion of the roof covering which is currently 75% progressed
  • Progression of the joinery elements to apartments and communal areas
  • Progression of the tiling to apartments which is currently 25% completed
  • Further delivery of kitchens
  • Progression of the decoration elements to apartments and communal areas
  • Progression of the 1st fix and 2nd fix mechanical and electrical to apartments and communal areas

August 2020

So much has taken place over the last few months at Poet’s Place, including completion of the main structural steelwork.

All foundations, pile caps and ground beams have now been installed, concrete floors are in on the front elevation and the steel framed system has commenced to the superstructure walls. Fire protection and lightning protection is also ongoing.

Summary of Works Progressed

  • Earthworks, groundworks and the base course are complete to the building footprint.
  • All pile caps, foundations and ground beams have been installed.
  • Main structural steelwork is now complete including cold rolled steelwork and brickwork angle restraint.
  • Metaldeck and concrete floors have been completed to the front elevation.
  • Fire protection works have been carried out including the application of fire-retardant paint which is underway across the steelwork. They are 30% progressed.
  • Lightning protection and bonding works have been applied.
  • The steel framed system commenced to the superstructure walls and the SFS infill panels are 5% installed.
  • Structural staircases 100% complete.
  • External weatherboard has commenced.
  • Feature brickwork façade has started to the front elevation.

Works Scheduled

  • Completion of the structural metal decking.
  • Completion of the concrete floors.
  • Progression of fire protection.
  • Progression of the steel framed system.
  • Continue superstructure brickwork.
  • Initial delivery of the windows and glazing.
  • Installation of the EPDM (weather sealing windows).
  • Commence the 1st fix mechanical and electrical phase.
  • Setting out of apartments.
  • Achieve wind and watertight status in September 2020.

May 2020

Demolition and alterations are now 100% complete at Poet’s Place and the construction phase has begun.

After existing units are now successfully demolished, the construction phase has commenced. A number of tasks such as groundworks, earthworks, piling and excavation have taken place.

Summary of Works Progressed

  • Construction phase works have commenced.
  • Party wall schedule of condition has been carried out by the party wall surveyor.
  • Asbestos has been removed from existing units.
  • The site compound has been established and existing units have been demolished.
  • The breaking up and disposal of existing slabs and foundation has progressed.
  • Concrete has been crushed for use of hardstanding.
  • Earthworks and groundworks have both made progress.
  • Completion of piling and pile caps have been cut down ready for foundations.
  • Reinforcement cages ready for insertion into ground beams and pile caps.
  • Pile caps and ground beams excavated.
  • Shuttering and concreting works to pile caps and ground beams progressed.
  • Steelwork design completed and fabrication commenced.

 

Works Scheduled

  • Completion of excavation for pile caps and ground beams.
  • Complete the insitu concrete to pile caps and ground beams.
  • Complete the ground floor slab to the underside of tarmac wearing course.
  • Disposal of earthworks and any sundry filling.
  • Fabrication of steelwork.

February 2020

All site investigations and geoenvironmental surveys are now 100% complete.

During the last quarter of preconstruction activity at Poet’s Place, site investigations and geoenvironmental surveys have been successfully undertaken with no contamination or unforeseen items uncovered. An asbestos survey has also been carried out with a formal report to come, but the initial feedback from the surveyor is that no obvious asbestos items were found. The final preparations are in place before starting demolition and construction on site in the next period.

 

Summary of Works Progressed

  • Appointment of Party Wall Surveyor, Building Control, Principle Designer, Principle Contractor, Contract Administrator Fire Consultant, Acoustician, Services Consultant and Structural Engineer.
  • Site investigations and geo-environmental surveys are 100% complete and no contamination issues or unforeseen items were uncovered.
  • An asbestos survey has been undertaken and is now 100% complete, awaiting formal report.
  • Initial Party Wall Notice has been issued and is 100% complete.
  • All contractor proposals have been finalised and agreed.
  • The building warranty is out for tender.
  • The main contract and warranties are being prepared ready for issue.
  • The Information Release Schedule and Responsibility Matrix has been drawn up and issued to the design team in line with design delivery programme requirements.

 

Works Scheduled

  • When asbestos report is received, demolition can be enabled.
  • Soft strip out of existing units and site clearance.
  • Commencement of demolition operations.
  • Procurement of the structural steelwork.
  • Completion of the contract with the main contractor.
  • Design progression as per design deliverables programme.
  • Fire strategy design.
  • Procurement of the structural warranty.

November 2019

Site investigations are well underway at Poets Place.

The initial site perimeter clearance and stopping up order are both 100% complete and a number of other key pre-construction activities have progressed throughout the latest pre-construction period.

 

Summary of Works Progressed

  • Initial site perimeter clearance is now 100% complete.
  • The erection of hoarding is 70% complete.
  • Stopping up order now made 100% complete.
  • Site investigations and geo-environmental surveys are 40% complete.
  • The disconnection of existing services has progressed to 50% completion.
  • Design team meeting was undertaken.

 

Works Scheduled

  • Finalise and agree on contractors’ proposals.
  • Draw up the Release Schedule and Responsibility Matrix to be issued to the design team.
  • Undertake a full ground investigation survey including a uniaxial survey to be carried out and monitored.

August 2019

Pre-construction activities at Poets Place have started.

The commencement of pre-contract appointments with a number of professional teams, including the architect, structural engineers and health and safety has begun. Appointments have also begun with the construction design and management consultants and mechanical and electrical consultants.

 

Summary of Works Progressed

  • The architect has produced the proposed drawings and plans, coordinated with the structural, mechanical and electrical design requirements.
  • Mechanical and electrical teams have also delivered general arrangement drawings for every essential system to be implemented in the site.
  • The order has been placed with contractors to install the hoardings to the perimeter of the site. The removal of trees and large shrubs will also commence which will require the temporary closure of the highway.
  • Site investigations are then to be carried out over the next two weeks. A topographical survey will also be undertaken.

 

Works Scheduled

  •  Structural works are being planned out, with detailed working drawings created.
  • Photos will be sent upon the commencement of the tree removal and installation of the hoardings to show the progress made at the development.

2021

September 2021

All physical building work at Poet’s Place is now complete.

Testing and commissioning is underway and is 50% complete at this time.

Summary of Works Progressed

· All internal works have now been completed

· Work to the exterior of the building is completed

· Testing and commissioning 50% complete

Works Anticipated

· Complete testing and commissioning

· Official sign off

· Tenants to move in

May 2021

Progress has been exceptional at Poet’s Place and the site is now nearing completion.

Window pods, cladding and lift installation are just some of the tasks completed last month. Many of the apartments are now complete and undergoing snagging, with external works also nearing completion. Many of the remaining tasks will be fully complete shortly.

Summary of Works Progressed

  • Project and substation awaiting energisation
  • External cladding and window pods now completed
  • Lift installation now complete, subject to commissioning
  • Juliet balconies progressing well
  • Internal operations progressing as per the programme, with fit out works commenced for all internal trades
  • Partitions, tiling, flooring and painting all making good progress
  • 1st, 2nd and 3rd floor apartments complete and locked off with final snagging process underway
  • External works nearing completion

Works Anticipated

  • Complete internal fit out to apartments and communal areas
  • Complete decoration elements to apartments and communal areas
  • Complete final fix to apartments and communal areas
  • Complete external works
  • Complete the main internal parts of the development
  • Snagging throughout the building
  • Testing and commissioning

February 2021

Great progress has been maintained at Poet’s Place.

During this period, substation works have commenced alongside works for incoming utilities. Other areas have progressed such as cladding, brickwork and internal operations. Fit out for all internal trades is underway and the 1st floor units are now complete, subject to snagging.

Summary of Works Progressed

  • Substation works have now commenced.
  • Works for incoming utilities have commenced.
  • External cladding to upper floors has progressed well.
  • Brickwork has been progressed to all external elevations.
  • Mechanical and electrical 1st fix works have significantly progressed, with 2nd fix works progressed on early floors.
  • Internal operations are making progress as per the programme, with fit out works commenced for all internal trades.
  • Partitions, tiling, flooring, and painting are all well underway.
  • 1st floor apartments are now complete.
  • Snagging process underway on 1st floor units.

Works Anticipated

  • Progression of the superstructure brickwork and cladding.
  • Construction of the substation.
  • Progression to the internal fit out to apartments and communal areas.
  • Progression of the decoration elements to apartments and communal areas.
  • Completion of the 1st fix and progression of the 2nd fix mechanical and electrical works to apartments and communal areas.
  • Progression of the Juliet balconies.
  • Completion of the stair walls.
  • Second floor apartment completed and snagged.

2020

November 2020

Poet’s Place is making visible progress inside and out.

The external elevation brickwork has made great progress to all elevations, as well as the cladding. Inside the development, internal fit out works have commenced and 1st and 2nd fix mechanical and electrical are now well underway.

Summary of Works Progressed

  • External elevation brickwork progressed to all elevations and external works overall are 40% complete
  • External cladding to upper floor commenced
  • Mechanical and electrical 1st fix works significantly progressed and 40% complete overall
  • Mechanical and electrical 2nd fix commenced on early floors
  • Internal fit out works commenced for all internal trades, with partitions, tiling, flooring and painting all making good progress throughout the building up to the 7th floor
  • 1st floor apartments are now significantly complete
  • Lightning protection 80% complete

Works Scheduled

  • Progression of the superstructure brickwork
  • Completion of the roof covering which is currently 75% progressed
  • Progression of the joinery elements to apartments and communal areas
  • Progression of the tiling to apartments which is currently 25% completed
  • Further delivery of kitchens
  • Progression of the decoration elements to apartments and communal areas
  • Progression of the 1st fix and 2nd fix mechanical and electrical to apartments and communal areas

August 2020

So much has taken place over the last few months at Poet’s Place, including completion of the main structural steelwork.

All foundations, pile caps and ground beams have now been installed, concrete floors are in on the front elevation and the steel framed system has commenced to the superstructure walls. Fire protection and lightning protection is also ongoing.

Summary of Works Progressed

  • Earthworks, groundworks and the base course are complete to the building footprint.
  • All pile caps, foundations and ground beams have been installed.
  • Main structural steelwork is now complete including cold rolled steelwork and brickwork angle restraint.
  • Metaldeck and concrete floors have been completed to the front elevation.
  • Fire protection works have been carried out including the application of fire-retardant paint which is underway across the steelwork. They are 30% progressed.
  • Lightning protection and bonding works have been applied.
  • The steel framed system commenced to the superstructure walls and the SFS infill panels are 5% installed.
  • Structural staircases 100% complete.
  • External weatherboard has commenced.
  • Feature brickwork façade has started to the front elevation.

Works Scheduled

  • Completion of the structural metal decking.
  • Completion of the concrete floors.
  • Progression of fire protection.
  • Progression of the steel framed system.
  • Continue superstructure brickwork.
  • Initial delivery of the windows and glazing.
  • Installation of the EPDM (weather sealing windows).
  • Commence the 1st fix mechanical and electrical phase.
  • Setting out of apartments.
  • Achieve wind and watertight status in September 2020.

May 2020

Demolition and alterations are now 100% complete at Poet’s Place and the construction phase has begun.

After existing units are now successfully demolished, the construction phase has commenced. A number of tasks such as groundworks, earthworks, piling and excavation have taken place.

Summary of Works Progressed

  • Construction phase works have commenced.
  • Party wall schedule of condition has been carried out by the party wall surveyor.
  • Asbestos has been removed from existing units.
  • The site compound has been established and existing units have been demolished.
  • The breaking up and disposal of existing slabs and foundation has progressed.
  • Concrete has been crushed for use of hardstanding.
  • Earthworks and groundworks have both made progress.
  • Completion of piling and pile caps have been cut down ready for foundations.
  • Reinforcement cages ready for insertion into ground beams and pile caps.
  • Pile caps and ground beams excavated.
  • Shuttering and concreting works to pile caps and ground beams progressed.
  • Steelwork design completed and fabrication commenced.

 

Works Scheduled

  • Completion of excavation for pile caps and ground beams.
  • Complete the insitu concrete to pile caps and ground beams.
  • Complete the ground floor slab to the underside of tarmac wearing course.
  • Disposal of earthworks and any sundry filling.
  • Fabrication of steelwork.

February 2020

All site investigations and geoenvironmental surveys are now 100% complete.

During the last quarter of preconstruction activity at Poet’s Place, site investigations and geoenvironmental surveys have been successfully undertaken with no contamination or unforeseen items uncovered. An asbestos survey has also been carried out with a formal report to come, but the initial feedback from the surveyor is that no obvious asbestos items were found. The final preparations are in place before starting demolition and construction on site in the next period.

 

Summary of Works Progressed

  • Appointment of Party Wall Surveyor, Building Control, Principle Designer, Principle Contractor, Contract Administrator Fire Consultant, Acoustician, Services Consultant and Structural Engineer.
  • Site investigations and geo-environmental surveys are 100% complete and no contamination issues or unforeseen items were uncovered.
  • An asbestos survey has been undertaken and is now 100% complete, awaiting formal report.
  • Initial Party Wall Notice has been issued and is 100% complete.
  • All contractor proposals have been finalised and agreed.
  • The building warranty is out for tender.
  • The main contract and warranties are being prepared ready for issue.
  • The Information Release Schedule and Responsibility Matrix has been drawn up and issued to the design team in line with design delivery programme requirements.

 

Works Scheduled

  • When asbestos report is received, demolition can be enabled.
  • Soft strip out of existing units and site clearance.
  • Commencement of demolition operations.
  • Procurement of the structural steelwork.
  • Completion of the contract with the main contractor.
  • Design progression as per design deliverables programme.
  • Fire strategy design.
  • Procurement of the structural warranty.

2019

November 2019

Site investigations are well underway at Poets Place.

The initial site perimeter clearance and stopping up order are both 100% complete and a number of other key pre-construction activities have progressed throughout the latest pre-construction period.

 

Summary of Works Progressed

  • Initial site perimeter clearance is now 100% complete.
  • The erection of hoarding is 70% complete.
  • Stopping up order now made 100% complete.
  • Site investigations and geo-environmental surveys are 40% complete.
  • The disconnection of existing services has progressed to 50% completion.
  • Design team meeting was undertaken.

 

Works Scheduled

  • Finalise and agree on contractors’ proposals.
  • Draw up the Release Schedule and Responsibility Matrix to be issued to the design team.
  • Undertake a full ground investigation survey including a uniaxial survey to be carried out and monitored.

August 2019

Pre-construction activities at Poets Place have started.

The commencement of pre-contract appointments with a number of professional teams, including the architect, structural engineers and health and safety has begun. Appointments have also begun with the construction design and management consultants and mechanical and electrical consultants.

 

Summary of Works Progressed

  • The architect has produced the proposed drawings and plans, coordinated with the structural, mechanical and electrical design requirements.
  • Mechanical and electrical teams have also delivered general arrangement drawings for every essential system to be implemented in the site.
  • The order has been placed with contractors to install the hoardings to the perimeter of the site. The removal of trees and large shrubs will also commence which will require the temporary closure of the highway.
  • Site investigations are then to be carried out over the next two weeks. A topographical survey will also be undertaken.

 

Works Scheduled

  •  Structural works are being planned out, with detailed working drawings created.
  • Photos will be sent upon the commencement of the tree removal and installation of the hoardings to show the progress made at the development.

Future Completed Project Visualizations

Invest in Poets Place

View Property Details

Refer a Friend to RWinvest

Have you heard about our referral scheme? With our referral scheme, you can be rewarded by simply recommending a fellow investor to RWinvest.

Each time you refer someone to our properties, and they go on to make a sale, you’ll earn £500. It’s one of the easiest ways to generate a quick cash boost on top of your lucrative investment earnings!

If you have a friend or family member who’s thinking of buying an investment property, and you’re happy with the service you experienced with us, get in touch with us today to find out how to get involved with our referral scheme.

Exciting New Launch
Liverpool Prices from £94,950

Completed and Tenanted Student Accommodation

Central Liverpool Location

Desirable Manchester Location

Embankment Exchange

80% Units Sold

Manchester Prices from £225,950

6% Projected Rental Returns

Up to 34% Below Local Comparable

Invest From £50,000

The Hive

Creating a Buzz in the Luton Market

Luton Prices from £194,950

5% Rental Returns 

75% Sold Out - Units Selling Fast

Welcome, visitor!