Sky Gardens Construction Updates

The Latest on Sky Gardens

With a sophisticated, relaxed locale with ease-of-access to local transport, the Sky Gardens development offers a luxury alternative to investments directly in Liverpool’s city centre. Check back on this page for the latest Sky Gardens construction updates as they develop.

 

Current Progress

  • Near completion of fire safety systems
  • Second fix mechanical and electrical progress
  • Lift installation commenced

As well as 3rd floor works completing, over the period at Sky Gardens, large progress has been made to first fix mechanical and electrical works, fire safety systems and second fix joinery.

Other tasks taken place include the external render and brick slip installation, first fix joinery to lower floors and the commencement of lift installation. Boarding and plastering has also made great headway on the lower floors.

 

Summary of Works Progressed

  • 3rd floor works now completed with snagging now commencing.
  • Continued installations of kitchens and bathrooms to 1st floor.
  • Near completion of first fix mechanical and electrical works to lower floors.
  • Near completion of fire safety systems including sprinklers.
  • Near completion of second fix joinery and final fitting to 2nd floor.
  • Progression of boarding and plastering on lower floors.
  • Progression of second fix mechanical and electrical installations.
  • External render and brick slip installation continuing.
  • Progression of first fix joinery to lower floors.
  • Commencement of lift installation.

March 2021

A number of tasks continue to make progress whilst kitchens and sanitaryware installation commences at Sky Gardens.

Over previous weeks, areas that have made significant progress include first fix joinery, mechanical and electrical works, extraction works, fire safety works, plasterboard coverings and metal stud walls. Finishes to the upper floors are also ongoing.

 

Summary of Works Progressed

  • Kitchen installation has commenced.
  • Sanitaryware installation has commenced.
  • Ground floor drainage works are complete.
  • First fix joinery on the upper floors is making progress.
  • First fix mechanical and electrical work ongoing.
  • Finishes to upper floors have continued.
  • Extraction works continued.
  • Fire safety systems including sprinklers continue to be installed.
  • Metal stud walls still underway.
  • Progress to plasterboard coverings.

December 2020

During the last few weeks at Sky Gardens, a number of tasks have continued as well as completed.

Metal stud walls, fire safety systems and extraction works are all examples of work continuing at Sky Gardens. The builders work to allow for risers and lift shaft extension are both complete. Finishes and first fix joinery have commenced.

 

Summary of Works Progressed

  • Continuation of metal stud walls and plasterboard coverings.
  • Continuation of first fix mechanical and electrical works.
  • Continuation of fire safety systems including sprinklers.
  • Continuation the ground floor drainage works.
  • Completion of the builders work to allow for risers.
  • Completion of lift shaft extension.
  • Continuation of extraction works.
  • Continuation of plaster skim to upper floors.
  • Commencement of finishes to upper floors.
  • Commencement of first fix joinery to upper floors.

September 2020

Several activities have progressed well at Sky Gardens with the external render now complete.

First fix works and fire safety systems are now being commenced with the brick slip installation back on track.

Summary of Works Progressed

  • Progression of metal stud walls.
  • Progression of plasterboard coverings.
  • Commencement of first fix mechanical and electrical works.
  • Commencement of fire safety systems including sprinklers.
  • Completion of external render.
  • Brick slip installation has resumed.

March 2020

Further progression of key internal construction works has been underway at Sky Gardens.

During the last few weeks, Sky Gardens construction continues internally. Metal partitions are being installed and mechanical and electrical works are still ongoing.

 

Summary of Works Progressed

  • Further progression to the internal metal partitions works.
  • Continuation of mechanical and electrical works.
  • Ongoing works to the link bridge.

Works Scheduled

  • TBA

December 2019

At Sky Gardens in Liverpool, completion of many tasks have been achieved whilst other construction activities such as metal partitioning and mechanical and electrical works are making great progress.

There has been significant progress to both internal and external works at the site. New windows have been successfully installed and strip out works are 100% complete whilst works to the link bridge, brick slip installation and external render all keep pushing this project forward towards completion.

 

Summary of Works Progressed

  • Completion of strip out works has been achieved.
  • Completion of new window installation.
  • Near completion of insulation installation.
  • Progression of the external render as brick slip installation continues.
  • Progression of metal partitioning works internally.
  • Progression of mechanical and electrical works internally.
  • Progression of works to link bridge.

Works Scheduled

  • Continued internal works including mechanical and electrical installation, link bridge and metal partitioning.

September 2019

In the latest Sky Gardens construction update, progress has been made across multiple areas of construction throughout the development.

Many areas of construction are complete and further advancements have begun, paving the way for more development over the coming months.

 

Summary of Works Progressed

  •  Windows are now 100% installed throughout the development and internal partitioning is underway on the upper floors.
  • Demolition of the safe room near to the rear block is also complete, as well as the structural alterations made to the brick and blockwork walls.
  • The steelwork vent supports have been installed for the smoke vent and floor apertures have been infilled where redundant.
  • Scaffolding has been erected to the rear block to allow the existing plant room to receive cladding.
  • Main entrance doors and screen are installed, while structural steel framing has also been installed and progress has been made to the cement particle boards to the under-croft areas of the development.
  • The installation of brick slip cladding has commenced and the insulation which precedes this is 100% complete. The internal boarding has also started to be installed.

 

Works Scheduled

  • TBA

June 2019

 Following on from the last Sky Gardens construction update, there are a number of advancements being made with the development.

This latest update outlines the progress made on strip out works, insulation and rendering, blockwork, and other structural elements.

 

Summary of Works Progressed

  • The removal of existing windows is underway, with blockwork being added to secure new windows.
  • Internal partitions are currently being installed.
  • Strip works, insulation and rendering of link building, and ceilings and soffits work has been completed.

 

 

 Works Scheduled

  •  Windows are scheduled to be installed.
  • Cladding work is yet to commence.
  • Internal fixings are scheduled for continuation.

March 2019

The latest Sky Gardens construction update from the developer mainly entails the progression of the remaining strip out works, ceilings and soffits, and partition walls.

Contractors continue to liaise all the final details and packages for the site, and ongoing progress will be made over the coming months.

 

Summary of Works Progressed

  • Partition walls, ceilings and soffits, and remaining strip out works have progressed,
  • The development of structural steelworks is underway.
  • The contractor continues to liaise with the envelope contractor with regards to the final details for Sky Gardens.
  • Works to the external façade have begun.

 

Works Scheduled

  • Disabled car parking spaces and electric vehicle charging points are to be incorporated within the external works package.
  • Ongoing progression of strip out works, ceilings and soffits and partition walls will continue.

December 2018

The latest construction update for Sky Gardens deals with the removal of asbestos from the resident entrance area, and the completion of internal strip out.

The site is now prepared for internal works to progress further into the New Year and for the external façade to begin.

 

Summary of Works Progressed

  • Large filter fans have been set up to exhaust asbestos particles from the air, with thorough sealing of the affected area. Anything containing asbestos materials has also been removed.
  • Stud walls and electrics have been installed to the upper floors.
  • Internal strip out is now complete and Window frames and cladding fixtures are now going up on the outside of the building.
  • The old lift has been de-commissioned and removed, and furniture removal is complete.

 

Works Scheduled

  • Internal works are on schedule and are due to progress in the New Year.
  • External façade works will commence into the New Year.

September 2018

The latest Sky Gardens Construction Update details the setup of the site plus extensive strip out and removal of materials from the location to make way for new structures.

Main works include the removal of electrical fittings, the stripping out of ceilings, and the elimination of surplus materials.

 

Summary of Works Progressed

  • A full survey of the building and roof has been undertaken, scaffold erection is underway, and site hoarding is up.
  • Materials continue to be removed from the site and the removal of electrical fittings continues.
  • The fire strategy has been produced.
  • Internal strip out is nearing completion while ceiling strip outs continue to progress, with ceiling zones being cleaned out.

 

Works Scheduled

  • Further asbestos removal and remediation works will be carried out.
  • Window frames and other structural features are to be added, and progress with electrical structures will be made.

June 2018

Things are progressing well for the construction of the Sky Gardens development.

By June 2018, progress has been made in terms of design, planning, structural, mechanical and electrical works, and main contract works. The site is being well prepared for construction, with the removal of on-site materials and internal structures and fittings.

 

Summary of Works Progressed

  • Materials are being removed via skips on-site, along with the ongoing removal of the internal studwork and electrical fittings and the carpet and floor tile finishes. The removal of toilet cubicles and vanity units has also progressed.
  • The site hoarding has been erected, while internal strip out and ceiling strip outs continue to progress.
  • A full survey of the existing building has been carried out by the structural engineer. This includes pulling testing of the concrete structure of both the front and rear block in relation to supporting the new cladding system.
  • A survey has taken place to establish the incoming services, including electrics, water, telecoms and gas. The M&E engineer is working with the architect to finalise the relocation of the existing connections. A survey of the existing lift and lift shaft has also taken place.
  • The design team have been continuing to work together to finalise the designs with final plans nearing completion.
  • A drainage survey has been completed and alteration works have progressed.

 

Works Scheduled

  • A further asbestos survey is underway with any remediation works to also be carried out.
  • One of the current lifts needs to be a fire fighting lift. The M&E engineer is sourcing a suitable lift from lift manufacturers.
  • The current utility connections are to be disconnected and temporary supply provided.

2021

As well as 3rd floor works completing, over the period at Sky Gardens, large progress has been made to first fix mechanical and electrical works, fire safety systems and second fix joinery.

Other tasks taken place include the external render and brick slip installation, first fix joinery to lower floors and the commencement of lift installation. Boarding and plastering has also made great headway on the lower floors.

 

Summary of Works Progressed

  • 3rd floor works now completed with snagging now commencing.
  • Continued installations of kitchens and bathrooms to 1st floor.
  • Near completion of first fix mechanical and electrical works to lower floors.
  • Near completion of fire safety systems including sprinklers.
  • Near completion of second fix joinery and final fitting to 2nd floor.
  • Progression of boarding and plastering on lower floors.
  • Progression of second fix mechanical and electrical installations.
  • External render and brick slip installation continuing.
  • Progression of first fix joinery to lower floors.
  • Commencement of lift installation.

March 2021

A number of tasks continue to make progress whilst kitchens and sanitaryware installation commences at Sky Gardens.

Over previous weeks, areas that have made significant progress include first fix joinery, mechanical and electrical works, extraction works, fire safety works, plasterboard coverings and metal stud walls. Finishes to the upper floors are also ongoing.

 

Summary of Works Progressed

  • Kitchen installation has commenced.
  • Sanitaryware installation has commenced.
  • Ground floor drainage works are complete.
  • First fix joinery on the upper floors is making progress.
  • First fix mechanical and electrical work ongoing.
  • Finishes to upper floors have continued.
  • Extraction works continued.
  • Fire safety systems including sprinklers continue to be installed.
  • Metal stud walls still underway.
  • Progress to plasterboard coverings.

2020

December 2020

During the last few weeks at Sky Gardens, a number of tasks have continued as well as completed.

Metal stud walls, fire safety systems and extraction works are all examples of work continuing at Sky Gardens. The builders work to allow for risers and lift shaft extension are both complete. Finishes and first fix joinery have commenced.

 

Summary of Works Progressed

  • Continuation of metal stud walls and plasterboard coverings.
  • Continuation of first fix mechanical and electrical works.
  • Continuation of fire safety systems including sprinklers.
  • Continuation the ground floor drainage works.
  • Completion of the builders work to allow for risers.
  • Completion of lift shaft extension.
  • Continuation of extraction works.
  • Continuation of plaster skim to upper floors.
  • Commencement of finishes to upper floors.
  • Commencement of first fix joinery to upper floors.

September 2020

Several activities have progressed well at Sky Gardens with the external render now complete.

First fix works and fire safety systems are now being commenced with the brick slip installation back on track.

Summary of Works Progressed

  • Progression of metal stud walls.
  • Progression of plasterboard coverings.
  • Commencement of first fix mechanical and electrical works.
  • Commencement of fire safety systems including sprinklers.
  • Completion of external render.
  • Brick slip installation has resumed.

March 2020

Further progression of key internal construction works has been underway at Sky Gardens.

During the last few weeks, Sky Gardens construction continues internally. Metal partitions are being installed and mechanical and electrical works are still ongoing.

 

Summary of Works Progressed

  • Further progression to the internal metal partitions works.
  • Continuation of mechanical and electrical works.
  • Ongoing works to the link bridge.

Works Scheduled

  • TBA

2019

December 2019

At Sky Gardens in Liverpool, completion of many tasks have been achieved whilst other construction activities such as metal partitioning and mechanical and electrical works are making great progress.

There has been significant progress to both internal and external works at the site. New windows have been successfully installed and strip out works are 100% complete whilst works to the link bridge, brick slip installation and external render all keep pushing this project forward towards completion.

 

Summary of Works Progressed

  • Completion of strip out works has been achieved.
  • Completion of new window installation.
  • Near completion of insulation installation.
  • Progression of the external render as brick slip installation continues.
  • Progression of metal partitioning works internally.
  • Progression of mechanical and electrical works internally.
  • Progression of works to link bridge.

Works Scheduled

  • Continued internal works including mechanical and electrical installation, link bridge and metal partitioning.

September 2019

In the latest Sky Gardens construction update, progress has been made across multiple areas of construction throughout the development.

Many areas of construction are complete and further advancements have begun, paving the way for more development over the coming months.

 

Summary of Works Progressed

  •  Windows are now 100% installed throughout the development and internal partitioning is underway on the upper floors.
  • Demolition of the safe room near to the rear block is also complete, as well as the structural alterations made to the brick and blockwork walls.
  • The steelwork vent supports have been installed for the smoke vent and floor apertures have been infilled where redundant.
  • Scaffolding has been erected to the rear block to allow the existing plant room to receive cladding.
  • Main entrance doors and screen are installed, while structural steel framing has also been installed and progress has been made to the cement particle boards to the under-croft areas of the development.
  • The installation of brick slip cladding has commenced and the insulation which precedes this is 100% complete. The internal boarding has also started to be installed.

 

Works Scheduled

  • TBA

June 2019

 Following on from the last Sky Gardens construction update, there are a number of advancements being made with the development.

This latest update outlines the progress made on strip out works, insulation and rendering, blockwork, and other structural elements.

 

Summary of Works Progressed

  • The removal of existing windows is underway, with blockwork being added to secure new windows.
  • Internal partitions are currently being installed.
  • Strip works, insulation and rendering of link building, and ceilings and soffits work has been completed.

 

 

 Works Scheduled

  •  Windows are scheduled to be installed.
  • Cladding work is yet to commence.
  • Internal fixings are scheduled for continuation.

March 2019

The latest Sky Gardens construction update from the developer mainly entails the progression of the remaining strip out works, ceilings and soffits, and partition walls.

Contractors continue to liaise all the final details and packages for the site, and ongoing progress will be made over the coming months.

 

Summary of Works Progressed

  • Partition walls, ceilings and soffits, and remaining strip out works have progressed,
  • The development of structural steelworks is underway.
  • The contractor continues to liaise with the envelope contractor with regards to the final details for Sky Gardens.
  • Works to the external façade have begun.

 

Works Scheduled

  • Disabled car parking spaces and electric vehicle charging points are to be incorporated within the external works package.
  • Ongoing progression of strip out works, ceilings and soffits and partition walls will continue.

2018

December 2018

The latest construction update for Sky Gardens deals with the removal of asbestos from the resident entrance area, and the completion of internal strip out.

The site is now prepared for internal works to progress further into the New Year and for the external façade to begin.

 

Summary of Works Progressed

  • Large filter fans have been set up to exhaust asbestos particles from the air, with thorough sealing of the affected area. Anything containing asbestos materials has also been removed.
  • Stud walls and electrics have been installed to the upper floors.
  • Internal strip out is now complete and Window frames and cladding fixtures are now going up on the outside of the building.
  • The old lift has been de-commissioned and removed, and furniture removal is complete.

 

Works Scheduled

  • Internal works are on schedule and are due to progress in the New Year.
  • External façade works will commence into the New Year.

September 2018

The latest Sky Gardens Construction Update details the setup of the site plus extensive strip out and removal of materials from the location to make way for new structures.

Main works include the removal of electrical fittings, the stripping out of ceilings, and the elimination of surplus materials.

 

Summary of Works Progressed

  • A full survey of the building and roof has been undertaken, scaffold erection is underway, and site hoarding is up.
  • Materials continue to be removed from the site and the removal of electrical fittings continues.
  • The fire strategy has been produced.
  • Internal strip out is nearing completion while ceiling strip outs continue to progress, with ceiling zones being cleaned out.

 

Works Scheduled

  • Further asbestos removal and remediation works will be carried out.
  • Window frames and other structural features are to be added, and progress with electrical structures will be made.

June 2018

Things are progressing well for the construction of the Sky Gardens development.

By June 2018, progress has been made in terms of design, planning, structural, mechanical and electrical works, and main contract works. The site is being well prepared for construction, with the removal of on-site materials and internal structures and fittings.

 

Summary of Works Progressed

  • Materials are being removed via skips on-site, along with the ongoing removal of the internal studwork and electrical fittings and the carpet and floor tile finishes. The removal of toilet cubicles and vanity units has also progressed.
  • The site hoarding has been erected, while internal strip out and ceiling strip outs continue to progress.
  • A full survey of the existing building has been carried out by the structural engineer. This includes pulling testing of the concrete structure of both the front and rear block in relation to supporting the new cladding system.
  • A survey has taken place to establish the incoming services, including electrics, water, telecoms and gas. The M&E engineer is working with the architect to finalise the relocation of the existing connections. A survey of the existing lift and lift shaft has also taken place.
  • The design team have been continuing to work together to finalise the designs with final plans nearing completion.
  • A drainage survey has been completed and alteration works have progressed.

 

Works Scheduled

  • A further asbestos survey is underway with any remediation works to also be carried out.
  • One of the current lifts needs to be a fire fighting lift. The M&E engineer is sourcing a suitable lift from lift manufacturers.
  • The current utility connections are to be disconnected and temporary supply provided.
parallax-image

Invest in Sky Gardens

View Property Details

Refer a Friend to RWinvest

Have you heard about our referral scheme? With our referral scheme, you can be rewarded by simply recommending a fellow investor to RWinvest.

Each time you refer someone to our properties, and they go on to make a sale, you’ll earn £500. It’s one of the easiest ways to generate a quick cash boost on top of your lucrative investment earnings!

If you have a friend or family member who’s thinking of buying an investment property, and you’re happy with the service you experienced with us, get in touch with us today to find out how to get involved with our referral scheme.

3 Units Remaining

The Summit

Stylish Baltic Triangle Living

Liverpool Prices from £139,950

Assured 7% NET Rental Yields

15-20% Below Market Value

Invest From £35,000

ELEMENT - The Quarter

North West's First Eco-Development

Liverpool Prices from £74,950

8% NET Rental Return

300m Away From New £1bn Royal Hospital

10% Deposit

Off Market Manchester Apartments

Premium Residential Investment

Manchester Prices from £219,112

5.5% NET Rental Return

10% Deposit Required