Central Park Construction Updates
Situated in the Baltic Triangle, Central Park is a residential development focusing on health and wellbeing of tenants through its use of eco-friendly technologies and outdoor amenities. Luxury 1 and 2-bedroom apartments combine with a rooftop terrace, landscaped gardens and outdoor gym.
Q4 2025 Update
Strong momentum continues across Central Park with steady progress across both internal and external works. The development is visibly taking shape as key milestones are reached across all phases.
July, August, September Construction Progress
- Externally, the building’s final form is emerging. Cladding is now complete on Phases 1 to 3 with Phase 4 progressing well. Brickwork, window installations and Juliette balcony balustrades are all advancing, contributing to the defined and finished appearance of the façade.
- Internally, fit-out activity continues to build pace. In Phase 1, many apartments are now at an advanced stage with kitchens installed and final finishes such as flooring, tiling and decoration underway. Phases 2 and 3 are following closely behind with internal layout works progressing and initial fit-out starting across several levels. Remaining structural works are also being completed to enable continued progress throughout the building.
- Preparations for power-on and commissioning of key systems are also underway — a critical step in moving the development closer to completion.
External / Façade Works
Check out the latest External and Internal Works in Central Park
- Momentum across Central Park remains strong, with steady progress across all phases.
- The final form of the development is now clearly visible, signalling that construction is entering its final stages.
- Brickwork, window installations, and Juliette balcony railings are well underway, giving the buildings a high-quality, finished appearance.
- Overall, the exterior is now transforming from construction site to completed development — reinforcing investor confidence in timely delivery.
- Inside, fit-out works are progressing at pace, with visible transformation across all phases.
- Phase 1 apartments are now at an advanced stage — kitchens fitted, flooring laid, tiling and decorations ongoing, signalling near completion.
- Phases 2 and 3 are following closely, with internal layouts completed and fit-out activity ramping up across multiple floors.
- Remaining structural works are being finalised to ensure seamless progress throughout the building.
- Preparations for power-on and commissioning of key systems are underway — a major milestone that moves the project closer to handover.
Central Park, Construction Update – Q2 2025
Buy to Let Investment - Everything You Need to Know
Whether you're a first-time investor or growing your existing portfolio, be sure to read our essential guide with must-know information on investing in buy to let property in the UK.
Why Choose RWinvest?
Here is why you should choose RWinvest as your UK property investment company:
Contact Us
Want to Get in Touch?
Fill in the form to contact us today and a member of our award-winning property team will be in touch to help.