Rice Works Construction Updates
Part of the historic Heap’s Mill development, Rice Works sits in a prime central Liverpool location just off the city’s iconic waterfront. Once completed, this development will offer a range of opulent Manhattans, 1 and 2-bedroom apartments, and excellent onsite facilities, including a rooftop terrace, landscaped gardens and an outdoor gym.
Q3 2026 Update
Rice Works – Construction Update Q3 2026
Rice Works, Construction Updates – Q3 2026
Key Work Updates
Structural Progress
Major structural milestones achieved across both buildings – Construction progressed significantly during the quarter, with Rice works reaching the completion of the Level 10 floor slabs. The central structural cores and all staircases were completed, while supporting columns continued to advance to higher levels. These achievements mark an important stage in establishing the full form and stability of the development.
Interior Construction
Ground floor internal construction advanced – Work on the ground floor moved forward with the completion of internal wall construction, creating defined spaces within the buildings. At the same time, installation of ceiling ductwork within apartments and cable containment throughout corridor areas commenced, supporting the development of the buildings’ internal services.
Exterior Finishes
Preparation for the building envelope continued – Progress was made in preparing the exterior of the development, with specialist access systems fully installed to support façade works. Installation of the external framing system also commenced, marking the beginning of the next stage in shaping the buildings’ exterior appearance. In addition, a window sample panel received planning approval for its visual design, confirming the selected finish for the development.
Building Systems
Essential building services installation progressed – Installation of key drainage systems continued throughout the quarter, alongside the ongoing integration of internal service infrastructure. These works form an important part of the building’s core functionality and support the continued progression of internal construction.
Site Operations
Construction logistics supported continued site progress – Temporary construction infrastructure was further advanced, including the completion of crane infill works and the installation of a material hoist serving the lower levels of the development. These improvements have supported efficient movement of materials and construction activities across the site as work continued to progress.
Q2 2026 Update
Rice Works – Construction Update Q2 2026
Rice Works, Construction Updates – Q2 2026
Key Work Updates
Tower Crane Repositioned to Support Ongoing Works
Tower crane TC7 has been successfully removed and repositioned to the corner of Block B1. This strategic move supports the next phase of construction and improves site logistics as the structure continues to rise.
Level 6 Slabs Completed
Concrete pours for the Level 6 slabs in both Blocks B1 and B2 have been completed. Infrastructure for Rice Works now comes to life as the construction takes shape in the heart of Heaps Mill.
Core Progression
The reinforced concrete cores in both B1 and B2 have advanced up to Level 9. These cores form the primary vertical circulation and structural stability for Rice Works. Openings for doors and service routes are already cast into the precast panels, with temporary timber formers still in place around selected reveals as works continue to progress through the next stages of installation.
Stair Installation Underway
Stair installation in Block B1 and B2 has progressed up to Level 6, supporting safe access for operatives and enabling further works to continue at higher levels.
Early Window Testing in Progress
Initial window units have been installed within the concrete frame on selected levels, alongside temporary sheathing and weatherproofing membranes to support early-stage testing. Operatives are using mobile access platforms to assess installation details, ensuring alignment, sealing, and performance standards are met ahead of full façade rollout.
Q1 2026 Update
Rice Works – Construction Update Q1 2026
Rice Works – Construction Update Q1 2026
Key Work Updates
Precast core wall panels
Large precast concrete wall panels have been installed to form the new core, with vertical reinforcement bars projecting above for the next lift of concrete. Both precast concrete cores are actively progressing and are currently being erected up to around Level 1.5, indicating that works are moving beyond ground floor and into the first-floor structure.
Formed openings to core
Openings for doors and windows are already cast into the panels, with temporary timber formers still in place around the reveals.
Materials staged for lifting
Loose precast or steel sections are stacked on the slab in front of the core, ready for lifting into place by crane.
Access for reinforcement works
A mobile scissor lift is positioned in front of the core to provide safe access for fixing reinforcements.
Temporary stability measures
Temporary barriers and bracing are visible at openings at ground level, helping control access and maintain stability while the core is incomplete.
Ground floor slabs and drainage
Ground floor slabs and associated drainage runs to both blocks are almost complete, with only limited areas left for final pours and connection works.
Q3 2025 Update
Why Choose RWinvest?
Here is why you should choose RWinvest as your UK property investment company:
Contact Us
Want to Get in Touch?
Fill in the form to contact us today and a member of our award-winning property team will be in touch to help.