Maritime View Construction Updates
Maritime View in Liverpool is a luxury residential development offering stunning waterfront views of the Royal Albert Dock. The project features 1 and 2-bedroom apartments with premium fixtures, a spa, gym, and rooftop terrace. View the latest construction updates for this exciting development here.
Q1 2026 Update
Key Work Updates
Internal Apartment Progress – Flooring installation is actively underway, while kitchen appliances are being installed across multiple floors. These works highlight the accelerating pace of internal progress at Maritime View as the project continues to gather momentum.
Mechanical & Electrical Progress – First-fix mechanical and electrical installations are well underway, with pipework, cabling, and containment largely in place. These essential works are paving the way for second-fix connections, marking a significant step forward in the internal apartment progress.
Window Progress – Windows are now fully installed, making all floors water tight, giving the building a high-quality, finished appearance, and marking a major visual milestone as construction progresses.
Cladding Backing and Fire Safety Works Progressing – Cladding backing works are advancing across Levels 12, 13, and 14, including the installation of banding and fire breaks, enhancing façade quality, regulatory compliance, and long-term building safet
Lift Installation Complete – Both lifts have now been handed over and are ready for beneficial use, significantly improving site efficiency and marking an important step toward operational readiness.
Maritime view, Construction Update – Q1 2026
Maritime View – Construction Update Q1 2026
Q4 2025 Update
Recent Achievements
Roof Completed – The roof structure is now fully finished.
This means the building is protected from the weather, allowing interior work to continue faster and more efficiently.
Lift Installation Started – Work has begun on installing the building’s lifts.
Once working, these lifts will help with construction access and later be used by residents or staff.
Façade and Windows Progress – Windows are now installed on six floors.
This improves both the look of the building and its energy efficiency.
Internal Construction –
- Phase 1 (Levels 1–3) is complete, and these floors are ready for fit-out and finishes.
- Phase 1 is also underway on Levels 4, 5, and 13, showing steady progress throughout.
- Phase 2 has begun on Level 3, marking the start of the next stage of interior work.
Fire Safety Improvements –
- Firestopping (materials that prevent fire spread) is complete on Levels 1–3.
- Automatic Opening Vent (AOV) hatches are installed on the roof and stairwells to release smoke in emergencies, improving safety and meeting regulations.
Maritime view, Construction Update – Q1 2026
Maritime View, Construction Update – Q4 2025
Q2 2025 Update
Maritime View, Construction Update – Q2 2025 – Part Two
Q1 2025 Update
Maritime View Construction Update, Q1 2025
Q4 2024 Update
Q3 2024 Update
Why Choose RWinvest?
Here is why you should choose RWinvest as your UK property investment company:
Contact Us
Want to Get in Touch?
Fill in the form to contact us today and a member of our award-winning property team will be in touch to help.