Maritime View Construction Updates
Maritime View in Liverpool is a luxury residential development offering stunning waterfront views of the Royal Albert Dock. The project features 1 and 2-bedroom apartments with premium fixtures, a spa, gym, and rooftop terrace. View the latest construction updates for this exciting development here.
Q2 2026 Update
Maritime view, Construction Update – Q2 2026
Maritime View, Construction Update – Q2 2026
Key Work Updates
Show Apartment Completed – Level 13
The show flat has now been fully completed and furnished. This milestone offers investors a clear insight into the premium finish, contemporary styling, and attention to detail that will define the completed residences.
Ground Floor M&E Installation Underway
Mechanical and electrical works have commenced on the ground floor, laying the foundations for essential building services. This area will form a key part of the resident experience, creating a welcoming and functional entrance space.
Tiling Completed – Levels 9 to 13
Floor and wall tiling has now been completed across Levels 9 through 13. This marks a major step forward in the finishing stages, with interiors now showcasing a clean, modern aesthetic throughout.
Joinery and Kitchen Installation – Levels 7 to 9
Joinery works and kitchen installations are progressing well across mid-level floors. These additions are significantly enhancing the visual progress within each apartment, helping to bring the final design vision to life.
Sanitaryware Installation – Multiple Levels
Bathroom installations are advancing across Levels 5 and 10 through 13, with modern sanitaryware being fitted in line with the development’s premium specification.
Lift Operational for Construction Use
The on-site lift has now been switched to beneficial use, improving site logistics and enabling more efficient movement of materials and workforce across all levels.
Firestopping Works Completed
Corridor and lift lobby firestopping has been fully completed, ensuring compliance with safety standards and preparing these areas for final decorative finishes.
Electrical Live Testing Progressing
Electrical live testing is currently underway across Levels 3, 4, 5, and 11 through 13. These checks are a key step in ensuring all systems meet required performance and safety standards ahead of final commissioning.
Booster Set Commissioned
The building’s water booster system has now been successfully commissioned, marking another important milestone in the delivery of core infrastructure.
Q1 2026 Update
Maritime view, Construction Update – Q1 2026
Maritime View – Construction Update Q1 2026
Key Work Updates
Internal Apartment Progress
Flooring installation is actively underway, while kitchen appliances are being installed across multiple floors. These works highlight the accelerating pace of internal progress at Maritime View as the project continues to gather momentum.
Mechanical & Electrical Progress
First-fix mechanical and electrical installations are well underway, with pipework, cabling, and containment largely in place. These essential works are paving the way for second-fix connections, marking a significant step forward in the internal apartment progress.
Window Progress
Windows are now fully installed, making all floors water tight, giving the building a high-quality, finished appearance, and marking a major visual milestone as construction progresses.
Cladding Backing and Fire Safety Works Progressing
Cladding backing works are advancing across Levels 12, 13, and 14, including the installation of banding and fire breaks, enhancing façade quality, regulatory compliance, and long-term building safet
Lift Installation Complete
Both lifts have now been handed over and are ready for beneficial use, significantly improving site efficiency and marking an important step toward operational readiness.
Q4 2025 Update
Maritime view, Construction Update – Q1 2026
Maritime View, Construction Update – Q4 2025
Recent Achievements
Roof Completed – The roof structure is now fully finished.
This means the building is protected from the weather, allowing interior work to continue faster and more efficiently.
Lift Installation Started – Work has begun on installing the building’s lifts.
Once working, these lifts will help with construction access and later be used by residents or staff.
Façade and Windows Progress – Windows are now installed on six floors.
This improves both the look of the building and its energy efficiency.
Internal Construction –
- Phase 1 (Levels 1–3) is complete, and these floors are ready for fit-out and finishes.
- Phase 1 is also underway on Levels 4, 5, and 13, showing steady progress throughout.
- Phase 2 has begun on Level 3, marking the start of the next stage of interior work.
Fire Safety Improvements –
- Firestopping (materials that prevent fire spread) is complete on Levels 1–3.
- Automatic Opening Vent (AOV) hatches are installed on the roof and stairwells to release smoke in emergencies, improving safety and meeting regulations.
Q2 2025 Update
Maritime View, Construction Update – Q2 2025 – Part Two
Q1 2025 Update
Maritime View Construction Update, Q1 2025
Q4 2024 Update
Q3 2024 Update
Why Choose RWinvest?
Here is why you should choose RWinvest as your UK property investment company:
Contact Us
Want to Get in Touch?
Fill in the form to contact us today and a member of our award-winning property team will be in touch to help.