The Mill Construction Updates - RWinvest Skip to content

The Mill Construction Updates

The centrepiece of the historic Heap’s Mill redevelopment project, this iconic Grade II listed rice mill is being transformed into a luxury residential building right on the edge of the Royal Albert Dock. Comprising luxury Manhattan, 1 and 2-bedroom apartments, as well as an underground spa and stunning rooftop bar, the Mill is soon to be one of Liverpool’s most desirable residences.

Q3 2024 Update

Video Thumbnail
26 Nov, 2024 1:07min

The Mill – Construction Update Q3 2024

July, August & September Construction Progress

Q3 2024

Significant progress was made with the substation structure completed and mains power connection work underway. Internal demolition also advanced while cast iron columns and window shutters were removed.

In the coming months, the site team will focus on constructing the cantilevered scaffold and removing loose materials in key zones across the site.

Arrow left
Arrow right

Q2 2024 Update

Video Thumbnail
01 Jun, 2024 46sec

The Mill – Construction Update Q2 2024

April, May & June Construction Progress

Q2 2024

Steady progress continued at The Mill throughout the second quarter of the year. The façade retention scheme is now complete on all elevations, and work has also begun on the development substation. With the façade retention scheme finished, internal demolition has recommenced, and the tower crane has been mobilised. As part of this delicate renovation process, the building’s intricate wooden frame and internal flooring are also being stripped out.

Arrow left
Arrow right

The North West Region Is Forecast to See the UK's Highest Five-Year Capital Growth Rate in 2025 and Beyond!

Read more about this in our guide to the latest Savill's Residential Property Market Forecast and learn which UK regions to consider for buy to let investment.

    Q1 2024 Update

    January, February & March Construction Progress

    Q1 2024

    In the first quarter of the year, the site team completed the removal of the building’s original roof and continued with the clearance of the upper floors. 

    A façade retention scheme has also been commenced around the building to enable the internal strip-out and structural works to commence. Scaffolding is now in place to allow the on-site team to continue with these works safely. 

    The Mill Q1 2024
    The Mill Q1 2024
    The Mill Q1 2024
    The Mill Q1 2024
    The Mill Q1 2024
    Arrow left
    Arrow right

    Exciting New Liverpool Development With Assured Year 1 Returns From £10,497

    Enquire About SoapWorks Today, a Stylish New Addition to Liverpool's Evolving Cityscape. Prices From Just £174,950 With 6% NET Yields.

      Q4 2023 Update

      October, November & December Construction Progress

      Q4 2023

      Following the removal of the original atrium in the previous period, the on-site team focused on the safe removal of asbestos from the building for much of Q4. 

      Piling and concreting were also carried out for the structural base of the tower crane, which is required to enable the erection of the crane. The site team also began removing the building’s original roof and clearing the upper floors towards the end of the year.

      The Mill Q4 2023
      The Mill Q4 2023
      The Mill Q4 2023
      The Mill Q4 2023
      The Mill Q4 2023
      Arrow left
      Arrow right

      Discover West One Manchester – Your Path to High-Yield Investments in 2025!

      Modern Salford living with stylish units, luxury facilities, 6% projected NET returns, and excellent capital growth. Secure your future in Manchester's booming property market now.

      Q3 2023 Update

      July, August & September Construction Progress

      Q3 2023

      Removal of the existing roof structure remained a priority for the on-site team throughout Quarter Three. In addition, most of the parapet walls were also reduced in height with coping stones and salvageable bricks stored for reinstatement and reuse during the construction process.

      In September, the demolition of the existing substation and the removal of the atrium were also completed as steady progress continues to be made to the internal strip-out.

      THE MILL
      THE MILL
      THE MILL
      THE MILL
      The Hive - Construction Update - Q3
      Arrow left
      Arrow right

      Don't Miss Your Copy of Our 2025 Property Market Predictions Guide

      Read our helpful guide now for a look back on what happened to the UK property market in 2024, and learn the key predictions you should know about for 2025. Access your free guide now!

        Q2 2023 Update

        April, May & June Construction Progress

        Q2 2023

        Throughout Quarter Two, the team’s focus remained on the necessary preparations for the commencement of construction works. In June, the delicate process of removing the existing roof began along with the demolition of the substation.

        During this period, technical design team meetings continued between the main contractor and project consultants. Removal of the atrium also continued as well as that of an asbestos insulation board by specially appointed contractors.

        THE MILL - Q2 2023
        THE MILL - Q2 2023
        THE MILL - Q2 2023
        THE MILL - Q2 2023
        THE MILL - Q2 2023
        Arrow left
        Arrow right

        Discover West One Manchester – Your Path to High-Yield Investments in 2025!

        Modern Salford living with stylish units, luxury facilities, 6% projected NET returns, and excellent capital growth. Secure your future in Manchester's booming property market now!

          Q1 2023 Update

          January, February & March Construction Progress

          Q1 2023

          The first three months of the year saw the on-site team commence and complete the demolition of the façade walls to the North and South of the atrium. Modern canopies were also removed on the same elevations in preparation for delicate restoration works.

          As The Mill is Grade II listed, an inventory of protected elements was compiled to create a record of important items and determine what actions are required to maintain and protect them.

          THE MILL - Q1 2023
          THE MILL - Q1 2023
          THE MILL - Q1 2023
          THE MILL - Q1 2023
          THE MILL - Q1 2023
          Arrow left
          Arrow right

          Secure a Luxury Investment Property Near London With Just £5k!

          Exciting new payment options at The Hive Luton! Secure your unit today with just £5k, pay only 10% on exchange, and settle the remaining 90% on completion. Hurry—limited units remain! Don’t miss this incredible opportunity to own a stylish, high-spec home on the London commuter belt.

            Why Choose RWinvest?

            Here is why you should choose RWinvest as your UK property investment company:

            We have over 2,000 five-star Trustpilot reviews

            Multiple Award Icon

            We're a multi-award winning investment company

            We offer investments in the best buy to let areas

            Arrow left
            Arrow right

            Contact Us

            Want to Get in Touch?

            Fill in the form to contact us today and a member of our award-winning property team will be in touch to help.

              It will be my third investment apartment with RW Invest and I cannot recommend them highly enough. Sean Orrett and Chloe Walker really do go the extra mile. Chloe in particular helped me through a particularly hard time with solicitors and all the paperwork that was involved. Living in a different country and negotiating all the nuances that come with investing, she negotiated with ease and gusto. A big thanks to you both.

              Margaret Wiele

              Daniel Stewart, has assisted me every step of the way. This is my first property purchase and so took Daniel up on his offer to guide me through every step no matter how small. I felt comforted to have his assistance in documents I needed to both understand and sign. Couldn't be happier with the help and customer care I have received so far.

              Nathan Saxon

              We highly recommend RW Invest to anyone looking for an experienced, reliable and knowledgeable professional company.
              We are more than delighted with their services throughout the entire process. They provided us with extremely helpful advice and guidance every step of the way and ensured that we understood all aspects involved in securing a property through them.

              Stephanie Chidlow

              Chloe is very helpful. She has been a great help and solved all the difficulties I had with the purchase. I am happy she was there to help with the process. Very approachable and responsible.

              Muhammad Atif

              This was my second unit purchase with RWinvest, and I found the team to be very helpful in finding the best deal which suited my needs and budget. Arjun Surana, Adam Burns were really processional in answering all questions, Excellent follow up and ensures your property purchase are smooth from the start to end and supporting throughout the purchase/exchange of contract process.
              I highly recommend anyone to purchase their property with RWinvest.

              Dhote

              Arrow left
              Arrow right
              Liverpool