View RWinvest Construction Updates
Structural Concrete Frame Complete

Bridgewater Wharf

Luxury Waterfront Living

Manchester Last Updated July 2021
  • Structural concrete frame complete
  • Block C external envelope roof works underway
  • Windows due to commence soon
3rd Floor Complete

Sky Gardens

Below Market Value Apartments

Liverpool Last Updated July 2021
  • Near completion of fire safety systems
  • Second fix mechanical and electrical progress
  • Lift installation commenced
Furniture Fittings Underway

Fabric District Residence

Premium Micro-Apartments

Liverpool Last Updated July 2021
  • Masonry works continue
  • First fix electrical has now been installed to the 5th floor
  • Plumbing first fix installed to the 3rd floor
New Site Boundary Erected

The Summit

Stylish Baltic Triangle Living

Liverpool Last Updated June 2021
  • Removal of debris and sub-standard materials
  • Surveys undertaken by structural engineers, architects, and contractors
  • New bathrooms ordered
Ground Floor Slab Pour Commenced

City Residence Apartments

Deluxe Apartments With Balconies

Liverpool Last Updated June 2021
  • Foundations Nearing Completion
  • Commencement of Sub Structure Brickwork
  • Ground Floor Slab Pour Commenced
Weatherboarding Complete

Parliament Square The Tower

L1 City Centre Postcode

Liverpool Last Updated May 2021
  • Structural framework forming external walls complete
  • Flat roof structure complete
  • External wall cladding and insulation 45% progressed
Excellent Progress Made

Parliament Square

Final Units Remaining - 98% Sold Out

Liverpool Last Updated May 2021
  • Block A partition walls completed
  • Block A apartment ceilings and wall and floor tiling installed
  • Block B podium steel structure and concrete pour 95% progressed
Site Demolition Commenced

Merchant's Wharf

Salford Waterfront Apartments

Manchester Last Updated May 2021
  • Site set up ongoing
  • Stage 2 site investigation works complete
  • Main demolition commenced
Nearing Completion

Poets Place

Dual-Use Apartments

Liverpool Last Updated May 2021
  • Cladding and window pods now complete
  • 1st, 2nd and 3rd floor units undergoing snagging
  • External works nearing completion
Contractors Commenced On Site

ELEMENT - The Quarter

North West's First Eco-Development

Liverpool Last Updated May 2021
  • Site prepared for contractors
  • Intumescent paint and primer to steel frame commenced
  • Metal floor decking to commence shortly
Substructure Brickwork Complete

One Baltic Square

Voted Coolest Place to Live

Liverpool Last Updated March 2021
  • Weatherboard installation 80% complete
  • Substructure brickwork complete
  • Steel frame structure nearly complete to Blocks D and A
Practical Completion

Crosby Gardens

Voted Top 10 Places to Live in UK

Liverpool Last Updated November 2020
  • Crosby Gardens has reached practical completion
  • Certificate was issued on 13th November
  • Works to the external areas are nearing completion
First 3 Phases Complete

Kings Dock Mill

Iconic New Development

Liverpool Last Updated October 2020
  • First three phases now complete
  • Final preparations underway to welcome occupants
  • Further 33 units scheduled for completion this quarter
Now Complete

Reliance House Studios

Premium Studio Apartments

Liverpool Last Updated August 2020
  • Reliance House Studios has received official confirmation of completion
  • The apartments have been finished to the highest standard
  • Tenants to move in imminently
Now Complete

Reliance House

Phased Refurbished Development Complete

Liverpool Last Updated August 2020
  • Reliance House Studios has received official confirmation of completion
  • The apartments have been finished to the highest standard
  • Tenants to move in imminently
Communal Areas Progress

Hamilton Hub

Spacious Studios and Student Rooms

Liverpool Last Updated July 2020
  • Communal areas and facilities under construction
  • More furniture installed to units
  • Plumbing ready to be connected
Structural Concrete Frame Complete

Bridgewater Wharf

Luxury Waterfront Living

Manchester Last Updated July 2021
  • Structural concrete frame complete
  • Block C external envelope roof works underway
  • Windows due to commence soon
3rd Floor Complete

Sky Gardens

Below Market Value Apartments

Liverpool Last Updated July 2021
  • Near completion of fire safety systems
  • Second fix mechanical and electrical progress
  • Lift installation commenced
Furniture Fittings Underway

Fabric District Residence

Premium Micro-Apartments

Liverpool Last Updated July 2021
  • Masonry works continue
  • First fix electrical has now been installed to the 5th floor
  • Plumbing first fix installed to the 3rd floor
New Site Boundary Erected

The Summit

Stylish Baltic Triangle Living

Liverpool Last Updated June 2021
  • Removal of debris and sub-standard materials
  • Surveys undertaken by structural engineers, architects, and contractors
  • New bathrooms ordered
Ground Floor Slab Pour Commenced

City Residence Apartments

Deluxe Apartments With Balconies

Liverpool Last Updated June 2021
  • Foundations Nearing Completion
  • Commencement of Sub Structure Brickwork
  • Ground Floor Slab Pour Commenced
Weatherboarding Complete

Parliament Square The Tower

L1 City Centre Postcode

Liverpool Last Updated May 2021
  • Structural framework forming external walls complete
  • Flat roof structure complete
  • External wall cladding and insulation 45% progressed
Excellent Progress Made

Parliament Square

Final Units Remaining - 98% Sold Out

Liverpool Last Updated May 2021
  • Block A partition walls completed
  • Block A apartment ceilings and wall and floor tiling installed
  • Block B podium steel structure and concrete pour 95% progressed
Site Demolition Commenced

Merchant's Wharf

Salford Waterfront Apartments

Manchester Last Updated May 2021
  • Site set up ongoing
  • Stage 2 site investigation works complete
  • Main demolition commenced
Nearing Completion

Poets Place

Dual-Use Apartments

Liverpool Last Updated May 2021
  • Cladding and window pods now complete
  • 1st, 2nd and 3rd floor units undergoing snagging
  • External works nearing completion
Contractors Commenced On Site

ELEMENT - The Quarter

North West's First Eco-Development

Liverpool Last Updated May 2021
  • Site prepared for contractors
  • Intumescent paint and primer to steel frame commenced
  • Metal floor decking to commence shortly
Substructure Brickwork Complete

One Baltic Square

Voted Coolest Place to Live

Liverpool Last Updated March 2021
  • Weatherboard installation 80% complete
  • Substructure brickwork complete
  • Steel frame structure nearly complete to Blocks D and A
Practical Completion

Crosby Gardens

Voted Top 10 Places to Live in UK

Liverpool Last Updated November 2020
  • Crosby Gardens has reached practical completion
  • Certificate was issued on 13th November
  • Works to the external areas are nearing completion
First 3 Phases Complete

Kings Dock Mill

Iconic New Development

Liverpool Last Updated October 2020
  • First three phases now complete
  • Final preparations underway to welcome occupants
  • Further 33 units scheduled for completion this quarter
Now Complete

Reliance House Studios

Premium Studio Apartments

Liverpool Last Updated August 2020
  • Reliance House Studios has received official confirmation of completion
  • The apartments have been finished to the highest standard
  • Tenants to move in imminently
Now Complete

Reliance House

Phased Refurbished Development Complete

Liverpool Last Updated August 2020
  • Reliance House Studios has received official confirmation of completion
  • The apartments have been finished to the highest standard
  • Tenants to move in imminently
Communal Areas Progress

Hamilton Hub

Spacious Studios and Student Rooms

Liverpool Last Updated July 2020
  • Communal areas and facilities under construction
  • More furniture installed to units
  • Plumbing ready to be connected

Construction Updates - Chat to an Agent

View our RWinvest Portfolio Record

Developments
Launched

134

Developments
in Construction

13

Developments
Completed

121

Total Value
of Projects Launched

£1billion

Find Your Ideal Investment Property

Start Search

What do we offer?