Central Park Construction Updates

Situated in the Baltic Triangle, Central Park is a residential development focusing on health and wellbeing of tenants through its use of eco-friendly technologies and outdoor amenities. Luxury 1 and 2-bedroom apartments combine with a rooftop terrace, landscaped gardens and outdoor gym. Here are the latest Central Park construction updates for your viewing:

Q1 2024 Update

Video Thumbnail
25 Apr, 2024

Central Park Q1 2024

January, February & March Construction Progress

Q1 2024

This period brought the commencement of ground floor concrete slab works and continuation of final pile cap installation in a busy start to the year for the site team. The basement dig-out and retaining walls are among the works to be completed in the next quarter.

Central Park - Q1 2024
Central Park - Q1 2024
Central Park - Q1 2024
Central Park - Q1 2024
Central Park - Q1 2024
Central Park - Q1 2024
Arrow left
Arrow right

Just 23-Mins from Central London

Premium London Commuter Belt apartments are securable for just £51,442, thanks to a new payment structure just agreed with the developer!

Q4 2023 Update

Video Thumbnail
25 Apr, 2024

Central Park Q4 2023

October, November & December Construction Progress

Q4 2023

Over the course of October and November, the piling mat was completed and on-site piling commenced. This is a significant milestone in terms of the progression of all other works at Central Park.

CENTRAL PARK - Q4
CENTRAL PARK - Q4
Central Park - Q4 2023
CENTRAL PARK - Q4
Central Park - Q4 2023
Arrow left
Arrow right

Just 23-Mins from Central London

Premium London Commuter Belt apartments are securable for just £51,442, thanks to a new payment structure just agreed with the developer!

Q3 2023 Update

July, August & September Construction Progress

Q3 2023

In Quarter Three, further progress was made by the team at Central Park as site clearance continued in preparation for on-site piling. This included breaking ground along with the preparation and construction of the piling mat.

In September, the jaw crusher was delivered to enable the installation of the piling mat, before the piling mat was then constructed in preparation for the piling rig.

Central Park - Q3 2023
Central Park - Q3 2023
Central Park - Q3 2023
Central Park - Q3 2023
Central Park - Q3 2023
Arrow left
Arrow right

How to Build a Property Portfolio, Get Started Now!

Tips on how to start building your property portfolio with tools for success.

Q2 2023 Update

April, May & June Construction Progress

Q2 2023

Several important progressions were made during this period in terms of procurement and design, which enabled site mobilisation to commence. Stage 4 design was completed in June, as well as a comprehensive CCTV survey.

A dilapidation survey for the site’s neighbouring Network Rail tunnel was also completed in Quarter Two, while drainage diversion works continued to progress significantly.

CENTRAL-PARK-Q2-2023 (1)
CENTRAL-PARK-Q2-2023 (2)
CENTRAL-PARK-Q2-2023 (3)
CENTRAL-PARK-Q2-2023 (4)
CENTRAL-PARK-Q2-2023 (5)
Arrow left
Arrow right

What is a Good Rental Yield? Find Out in Our FREE Guide

How to calculate rental yields, plus which UK hotspots offer the strongest rental returns.

Why Choose RWinvest?

Here are three reasons to choose RWinvest for your next UK property investment.

We have over 2,000 five-star Trustpilot reviews

Multiple Award Icon

We're a multi-award winning investment company

We offer investments in the best buy to let areas

Arrow left
Arrow right