Embankment Exchange Construction Updates

The Latest on Embankment Exchange

Two towering skyscrapers over Manchester City Centre, Embankment Exchange is a development offering deluxe residential apartments and outstanding amenities. A spa complete with swimming pool and convenient location in Greengate, a vibrant area of the city, create a winning investment opportunity. Here are the latest Embankment Exchange construction updates for your viewing:

Current Progress

  • Progression of slabs on Irwell and Greengate Building
  • Commencement of the steel framing system installation to the Irwell building
  • Installation of passenger and goods hoist to Level 20 Irwell building

2023

2022

At Embankment Exchange, the steel framing system has commenced on the Irwell tower and the superstructure has progressed across both the Irwell and Greengate buildings.

 

Goods hoist has been installed up to level 20 on the Irwell tower and scaffolding have also been installed to allow for mast climber installation in the next few weeks.

 

Summary of Works Progressed

  • Progression of superstructure on both Irwell and Greengate buildings
  • Progression of slabs on Irwell and Greengate Building
  • Commencement of the steel framing system installation to the Irwell building
  • Installation of passenger and goods hoist to Level 20 Irwell building
  • Installation of scaffolding for mast climbers to Irwell and Greengate building

Works Anticipated

  • Progression of superstructure on Irwell and Greengate building
  • Progression of the steel framing system installation to the Irwell building
  • Installation of mast climbers

During the last month at Embankment Exchange, there has been a lot of action on site.

 

Mobilisation of Careys and MTECH rig are underway. Structural remedial works are progressing and build strategy has been confirmed for the concrete frame, façade, glazing and external wall build-up. The tower crane has been serviced and material procurement are also ongoing throughout this time.

 

Summary of Works Progressed

  • Careys mobilisation commenced
  • The tower crane has been serviced and had a thorough examination
  • Material procurement ongoing
  • MTECH rig procurement commenced
  • MTECH rig mobilisation underway
  • Precast mobilisation progress
  • Careys due diligence has been undertaken
  • Mechanical, electrical and plumbing incoming and distribution works progressed
  • Structural remedial works underway
  • Confirmation of build strategy for concrete frame
  • Confirmation of build strategy for façade, glazing and external wall build-up
  • Procurement strategy planning ongoing for supply chain engagement – concrete superstructure, cladding, steel frame structure and carpentry

2023

At Embankment Exchange, the steel framing system has commenced on the Irwell tower and the superstructure has progressed across both the Irwell and Greengate buildings.

 

Goods hoist has been installed up to level 20 on the Irwell tower and scaffolding have also been installed to allow for mast climber installation in the next few weeks.

 

Summary of Works Progressed

  • Progression of superstructure on both Irwell and Greengate buildings
  • Progression of slabs on Irwell and Greengate Building
  • Commencement of the steel framing system installation to the Irwell building
  • Installation of passenger and goods hoist to Level 20 Irwell building
  • Installation of scaffolding for mast climbers to Irwell and Greengate building

Works Anticipated

  • Progression of superstructure on Irwell and Greengate building
  • Progression of the steel framing system installation to the Irwell building
  • Installation of mast climbers

2022

During the last month at Embankment Exchange, there has been a lot of action on site.

 

Mobilisation of Careys and MTECH rig are underway. Structural remedial works are progressing and build strategy has been confirmed for the concrete frame, façade, glazing and external wall build-up. The tower crane has been serviced and material procurement are also ongoing throughout this time.

 

Summary of Works Progressed

  • Careys mobilisation commenced
  • The tower crane has been serviced and had a thorough examination
  • Material procurement ongoing
  • MTECH rig procurement commenced
  • MTECH rig mobilisation underway
  • Precast mobilisation progress
  • Careys due diligence has been undertaken
  • Mechanical, electrical and plumbing incoming and distribution works progressed
  • Structural remedial works underway
  • Confirmation of build strategy for concrete frame
  • Confirmation of build strategy for façade, glazing and external wall build-up
  • Procurement strategy planning ongoing for supply chain engagement – concrete superstructure, cladding, steel frame structure and carpentry