Embankment Exchange Construction Updates

Two towering skyscrapers over Manchester City Centre, Embankment Exchange is a development offering deluxe residential apartments and outstanding amenities. A spa complete with swimming pool and convenient location in Greengate, a vibrant area of the city, create a winning investment opportunity. Here are the latest Embankment Exchange construction updates for your viewing:

Q1 2024 Update

Video Thumbnail
25 Apr, 2024

Embankment Exchange Q1 2024

January, February & March Construction Progress

Q1 2024

Final works for the installation of sheathing board, window framing and glazing progressed during this period. The onsite team have now commenced the installation of brick slips, providing a great view of the finish to be expected of the development’s façade.

Internally, major progress was made with internal framing and boarding, as well as other key works such as kitchens, bathrooms and flooring.

Arrow left
Arrow right

£50,000 Capital Growth Goldmine

With high-spec interiors and excellent amenities, these stunning back-to-market apartments offer top rental returns and capital growth!

    Q4 2023 Update

    Video Thumbnail
    25 Apr, 2024

    Embankment Exchange Q4 2023

    October, November & December Construction Progress

    Q4 2023

    Great progress was made across the site in the final quarter of 2023 as several key works progressed closer to completion. These included the sheathing board, window frames and glazing, among other important external works. The internal works package also progressed during this period, with kitchen installation, tiling, and floor finishes all commencing.

    Arrow left
    Arrow right

    £50,000 Capital Growth Goldmine

    With high-spec interiors and excellent amenities, these stunning back-to-market apartments offer top rental returns and capital growth!

      Q3 2023 Update

      Video Thumbnail
      25 Apr, 2024

      Embankment Exchange Q3 2023

      July, August & September Construction Progress

      Q3 2023

      In the period July-September, huge progress was made at Embankment Exchange on several fronts including the steel framing system, which was completed in all but the hoist apartments.

      Other key works that reached completion in Quarter Three included stair installation in the Irwell building and underground drainage in both buildings. Mechanical and electrical 1st fixes progressed well across the site, while curtain walling to the north elevation of the Irwell building moved nearer to completion.

      Embankment Exchange - Construction Update - Q3
      Embankment Exchange - Construction Update - Q3
      Embankment Exchange - Construction Update - Q3
      Embankment Exchange - Construction Update - Q3
      Embankment Exchange - Construction Update - Q3
      Arrow left
      Arrow right

      What is a Good Rental Yield? Find Out in Our FREE Guide

      How to calculate rental yields, plus which UK hotspots offer the strongest rental returns.

      Q2 2023 Update

      Video Thumbnail
      25 Apr, 2024 01:01

      Embankment Exchange – Q2 2023

      April, May & June Construction Progress

      Q2 2023

      Between April and June, works continued to advance as planned with further progress made to the erection of concrete frames in both towers. Installation of the staircase and stair structure in the Greengate Tower was completed, while great progress was made to the Irwell Tower’s steel frame structure.

      Wind liner and weatherboarding were among the key works to have commenced during this period, further advancing the external works package. Mast climbers were also installed to the internal and gable elevations, and windows for the lower floors were delivered to the sit for installation in Quarter Three.

      EE - Q2 2023
      EE - Q2 2023
      EE - Q2 2023
      EE - Q2 2023
      EE - Q2 2023
      Arrow left
      Arrow right

      Looking for a Stress-Free Investment?

      Secure a 2-bed townhouse for just £35,495, with nothing to pay until next year!

      Q1 2023 Update

      Video Thumbnail
      25 Apr, 2024 01:05

      Embankment Exchange Q1 2023

      January, February & March Construction Progress

      Q1 2023

      Early 2023 brought with it huge progress to the external structures of both towers at Embankment Exchange. Significant advances were made with the concrete frames, while the team also focused on the execution of the façade design with consultants and subcontractors.

      Walls and columns were also poured during this period, along with vertical elements up to level 35 on the Irwell Tower and Level 13 on the Greengate Tower.

      EE - Q1 2023
      EE - Q1 2023
      EE - Q1 2023
      EE - Q1 2023
      EE - Q1 2023
      Arrow left
      Arrow right

      How to Build a Property Portfolio, Get Started Now!

      Tips on how to start building your property portfolio with tools for success.

      Why Choose RWinvest?

      Here are three reasons to choose RWinvest for your next UK property investment.

      We have over 2,000 five-star Trustpilot reviews

      Multiple Award Icon

      We're a multi-award winning investment company

      We offer investments in the best buy to let areas

      Arrow left
      Arrow right

      Contact Us

      Want to Get in Touch?

      Fill in the form to contact us today and a member of our award-winning property team will be in touch to help.

        Customer Review Customer Review
        trustpilot google
        Manchester