The Latest on Heap’s Mill

Encompassing two blocks called Miller’s Place and The Mill, Heap’s Mill is a historic development in the heart of Liverpool city centre. A blend of new-builds and Grade listed restorations, Heap’s Mill combines luxury apartments with ground-breaking facilities in a lucrative, high-income buy to let investment. Here are the latest Heap’s Mill construction updates for your viewing:
Current Progress
- First formal design team meeting held
- Pre procurement of key components being investigated
- Detailed interior Drone surveys undertaken at the Mill
2022
Pre-construction activities at The Mill and Miller’s Place have begun.
The commencement of pre-contract appointments with a number of professional teams has taken place, including the architect, structural engineers and health and safety consultants. Appointments have begun with the construction design and management consultants, and the mechanical and electrical consultants.
There have also been a number of surveys done during the period on the Mill and a demolition strategy has been put together, with a specialist demolition firm appointed to oversee this important phase of the development. Detailed drone surveys were undertaken of the interiors of The Mill ahead of the start of construction, with safe access points identified and a detailed plan put together.
Summary of Works Progressed
- First formal design team meeting held
- Pre procurement of key components being investigated
- Architectural surveys ongoing
- Specialist demolition consultants appointed and demolition strategy works underway
- Integrated design, procurement and construction programme in preparation
- Construction logistics plan being formalised
- Detailed interior Drone surveys undertaken at the Mill
- Safe Access points and site plan identified following surveys
2022
November
Pre-construction activities at The Mill and Miller’s Place have begun.
The commencement of pre-contract appointments with a number of professional teams has taken place, including the architect, structural engineers and health and safety consultants. Appointments have begun with the construction design and management consultants, and the mechanical and electrical consultants.
There have also been a number of surveys done during the period on the Mill and a demolition strategy has been put together, with a specialist demolition firm appointed to oversee this important phase of the development. Detailed drone surveys were undertaken of the interiors of The Mill ahead of the start of construction, with safe access points identified and a detailed plan put together.
Summary of Works Progressed
- First formal design team meeting held
- Pre procurement of key components being investigated
- Architectural surveys ongoing
- Specialist demolition consultants appointed and demolition strategy works underway
- Integrated design, procurement and construction programme in preparation
- Construction logistics plan being formalised
- Detailed interior Drone surveys undertaken at the Mill
- Safe Access points and site plan identified following surveys