Parliament Square Construction Updates

The Latest on Parliament Square

See below for all of the Parliament Square construction updates, documenting how this promising Baltic Triangle development is flourishing through its consistent progress.

Current Progress

  • Block B completion of fire coating steel framework
  • Block B mast climber installation complete
  • Block D progress to retaining walls

Parliament Square has seen sufficient construction progress over the last period to Blocks B and D.

There has been progression to Block D’s retaining walls and concrete beam foundations and the internal staircase structure has commenced. Block B fire coating of the steel framework is now complete and window installation is nearing completion.

Summary of Works Progressed – Block B

  • Completion of fire coating steel framework
  • Sub-structure masonry wall is 55% complete
  • Finalisations to structural framework forming external walls
  • Finalisations to weatherboarding
  • Completion of above ground drainage
  • Finishing touches to structural framework forming external walls
  • Window installation is 97% complete
  • Clear progressions to brickwork elevations
  • 77% completion of apartment ceiling installation
  • Commencement of cladding installation
  • Completion of mast climber installation
  • Partition walls installation now 93% complete
  • Plaster finishes walls and ceilings is 67% complete
  • 70% completion of 1st fix electrical, plumbing and heating
  • Rapid progression of kitchen units and appliances
  • Doorframes are 65% complete with skirting and architrave 60% complete
  • Bathroom sanitary fittings 52% progressed
  • Wall and floor tiling as well as carpet and floor finishes are 61% complete
  • Doors and ironmongery 51% complete
  • 2nd fix electrical, plumbing and heating all 29% complete

In Block B, the structural framework forming the external walls is 93% progressed. Block D retaining walls and concrete beam foundations are underway.  

Works have progressed both internally and externally to Block B, which now sees the flat roof structure and covering 95% progressed, whilst brickwork to elevations has commenced. In Block D, piles have been cropped ready for removal from site, and Eazistrip reinforcement continuity systems are onsite ready for installation.  

Summary of Works Progressed – Block B 

  • Sub-structure masonry wall is 45% complete 
  • Structural framework forming external walls is 93% complete 
  • Fire coating to the steel framework is complete 
  • The flat roof structure and covering is making great progress and is now 95% progressed 
  • Podium steel structure and concrete pour 100% complete 
  • Weatherboarding is 93% progressed so far 
  • Window installation is also underway and 93% complete 
  • Brickwork to elevations has commenced 
  • Riser installation is 65% complete 
  • Partition walls  are 72% progressed 
  • Apartment ceilings are 73% complete 
  • Plaster finishes to walls and ceilings are ongoing 
  • 1st fix electrical works are 46% progressed and 1st fix plumbing and heating are 45% complete 
  • Kitchen units and appliances are being installed 
  • Doorframes are 32% progressed with skirting and architrave 23% complete. Doors and ironmongery commenced 
  • Bathroom sanitary fittings 16% progressed 
  • Wall and floor tiling is 27% progressed with carpet and floor finishes also ongoing 
  • 2nd fix electrical, plumbing and heating underway 

Summary of Works Progressed – Block D 

  • Retaining walls and concrete beam foundations are 5% complete 
  • Pile foundation load testing underway 
  • Steel reinforcement mesh, drainage, concrete manhole rings and other materials have arrived on site 
  • Shuttering in place for the contiguous wall concrete pour 
  • Steel cage reinforcement formed 
  • Eazistrip reinforcement continuity systems onsite ready  for installation 
  • Piles cropped ready for removal off site 
  • Formation of reinforcement for pile capping beams has commenced 
  • Steel reinforcement to the party wall 
  • Reducing of levels is ongoing 

Block A is now officially completed. Block D demolition continues whilst Block B sprinkler and first fix mechanical have commenced.

Work carries on across Blocks B and D as the development takes shape more and more every week.

Summary of Works Progressed – Block A

  • Flat roof coverings including balconies are 100% complete
  • External windows, doors and curtain walling are 100% complete
  • Brickwork and insulation complete
  • External wall cladding is completed
  • Inspection of works to completed apartments is complete
  • Carpet and floor finishes complete
  • Decorations are complete
  • Second fix works are complete
  • General fixtures and fittings are complete
  • This block is now 100% completed

Summary of Works Progressed – Block B

  • Concrete pour to upper suspended floor structure has been completed
  • Fire coating to steel framework is now 85% complete
  • Structural framework forming the external walls is 80% progressed
  • The podium steel structure is 95% complete
  • The podium concrete pour is also nearly complete at 95% progression so far
  • First fix mechanical has commenced
  • Sprinkler system commenced
  • Window installation ongoing

Summary of Works Progressed – Block D

  • Demolition and site clearance are 50% progressed

Many tasks have been completed this month at Parliament Square, including weatherboarding, above ground drainage and plaster finishes in Block A and the upper suspended steel floor structure is approaching completion in Block B.

Internal progress has made headway in Block A including the installation of kitchen units, doorframes, carpets and second fix electrical works. In Block B, fire coating to the steel framework has progressed well and the podium steel structure and concrete pour are 95% complete.

Summary of Works Progressed – Block A

  • Weatherboarding, above ground drainage, plaster finishes, partition walls, apartment ceilings and wall and floor tiling have all completed
  • Flat roof coverings including balconies are 95% complete
  • External windows, doors and curtain walling are 98% complete
  • Brickwork and insulation to elevations is 80% complete
  • External wall cladding is 25% progressed
  • The lift installation is nearly complete
  • Kitchen units and appliances are being installed
  • Doorframes are 95% complete
  • Skirting and architrave are 89% progressed so far
  • Bathroom sanitary fittings are 91% complete
  • Carpet and floor finishes are 69% complete
  • Doors and ironmongery are making great progress
  • Decorations are progressing well and are 85% progressed
  • Second fix electrical works are 86% progressed with plumbing and heating 67% complete
  • General fixtures and fittings are ongoing and are 21% complete thus far

Summary of Works Progressed – Block B

  • Upper suspended steel floor structure 90% complete
  • Concrete pour to upper suspended floor structure is 90% complete
  • Fire coating to steel framework is 40% complete
  • Structural framework forming the external walls is 12.5% progressed
  • The podium steel structure is 95% complete
  • The podium concrete pour is also nearly complete at 95% progression so far
  • Window installation commenced

February 2021

Block B concrete pour continues whilst Block A is making great internal progress.

In Block B, the steel frame structure is now complete and the concrete pour to the upper suspended floor structure is underway. In Block A, several tasks are approaching completion including flat roof coverings, weatherboarding, and external windows. First and second fix works are making excellent progress as well as other internal fit out works.

 

Summary of Works Progressed – Block A

  • Flat roof coverings and balconies are 95% complete.
  • Weatherboarding nearly complete at 99% progressed.
  • External windows, doors and curtain walling is 98% progressed.
  • Brickwork and insulation to elevations is 45% complete.
  • External wall cladding is commenced and 5% progressed so far.
  • Lift installation is 65% complete.
  • Above ground drainage is 85% progressed.
  • Partition walls installation has made good progress and is 92% complete.
  • Apartment ceiling installation, first fix electrical, plumbing and heating are all 85% complete.
  • Second fix electrical, plumbing and heating are 40% complete.
  • Plaster finishes to walls and ceilings are 60% progressed.
  • Door frames, skirting and architrave are all halfway there.
  • Kitchen units and appliances are 55% complete.
  • Bathroom sanitary fittings are 45% progressed.
  • Wall and floor tiling are 60% progressed with carpet and floor finishes now 40% complete.
  • Doors and ironmongery are ongoing at 10% progression so far.
  • Decorations are 35% complete with general fixtures and fittings underway.

 

Summary of Works Progressed – Block B

  • Steel frame structure 100% complete.
  • Floor slab construction 100% complete.
  • Retaining walls and concrete beam foundations 100% complete.
  • Internal staircase structure 100% complete.
  • Concrete pour to upper suspended floor structure 66% complete.

November 2020

Block A is progressing well, and construction of Block B has commenced.

Block B has received foundation works and concrete pour, as well as the steel frame delivery which has since commenced.

Summary of Works Progressed – Block A

  • Scaffolding complete
  • Internal staircase structure completed
  • Structural framework forming the external walls is 100% complete
  • Weatherboarding has made huge progress to 85% completion
  • Flat roof covering is 50% progressed
  • Sub-structure masonry walls are 40% complete
  • Internal partition walls are 40% complete
  • Mechanical services are 25% complete
  • Riser installation is ongoing
  • Core drilling services are almost complete
  • Window installation is 60% complete
  • Brickwork to elevations has commenced
  • Apartment ceiling installation has commenced and is 10% progressed so far

Summary of Works Progressed – Block B

  • Excavations and cage reinforcement concrete foundations
  • Reinforcement cages for pad foundations
  • Concrete foundations poured
  • Site clearance
  • Floor slab preparation
  • Concrete floor slab poured
  • Site preparation for steel frame delivery
  • Steel frame structure now 90% complete

August 2020

Construction works have been primarily to Block A with the steel frame structure now complete.

Other tasks completed include underground drainage, the internal staircase structure and floor slab construction.

Summary of Works Progressed

  • Site compound and supplies 100% complete.
  • Ground infill and site levelling complete.
  • Piling foundations complete.
  • Retaining walls and concrete beam foundations complete.
  • Underground drainage is complete.
  • Floor slab construction 100% complete.
  • Steel frame structure complete to Block A.
  • Upper suspended steel floor structure complete.
  • Internal staircase structure complete.
  • Fire coating to the steel framework is complete.
  • Structural framework forming external walls 20% progressed.
  • Internal partition walls 25% complete.
  • Mechanical services 5% complete.
  • Hoist installed.
  • Scaffolding commenced.
  • Temporary electrical supply installed.

May 2020

Parliament Square has seen great progress made to the basement car park, floor slab construction and Block A’s steel frame structure.

Other activities commenced during this time include further work to ground infill and levelling which is nearly 100% complete, progress to the retaining walls, pre-cast concrete staircases and the installing of easi-edge handrail system.

Summary of Works Progressed

  • Site compound and supplies 90% complete.
  • Significant progress to the steel frame structure on Block A which is 25% complete.
  • Steel reinforcement concrete slab and column structures 35% progressed.
  • Floor slab construction commenced 30%.
  • Further progress to ground infill and levelling which are 98% complete.
  • Retaining walls and concrete beam foundations progressed 60%.
  • Retaining walls and foundations to the basement car park.
  • Pre-cast concrete staircases installed.
  • Metal deck suspended and upper floor materials loaded.
  • Easi-edge handrail system installed.

February 2020

Ground infill is 90% progressed at Parliament Square with piling foundations 100% complete.

The progress at Parliament Square during this construction period has seen the formation of concrete retaining walls and steelwork has been put in place ready for the construction of columns.

Summary of Works Progressed

  • The site compound and temporary supplies are 50% complete with site floodlights and a site washdown cleaning facility now installed.
  • Ground infill and site levelling is nearly completed at 90%.
  • Piling foundations are 100% complete with piled retaining concrete walls formed.
  • Concrete retaining walls have progressed by 10% and service ducts have been formed in the walls. The retaining walls have been waterproofed.
  • Concrete beam foundations have commenced and are 10% complete.
  • Steelwork has been put in place for column construction and concrete pads have been formed to support these columns.
  • The crane pad is under construction.
  • Excavation to the sandstone car park base.

 

Works Scheduled

  • Construction of columns.

November 2019

With demolition complete, construction has begun at Parliament Square in Liverpool and work is progressing nicely.

There has been significant construction activity to the sub-structure and super-structure during the latest period, including the ground being infilled and levelled, and the progress of pilings and concrete foundations.

 

Summary of Works Progressed

• Demolition is now complete.
• Site clearance is 100% complete.
• Trial pit areas were marked out and dug as part of ground investigations.
• The site compound and temporary supplies have progressed by 50%.
• The ground is being infilled and levelled which has made great progress of 80%.
• Pilings and the concrete foundations have progressed by 60%. The pile foundation has formed the retaining wall.
• Reinforced steel cages are on site and prepared.

 

Works Scheduled

• Reinforced steel cages ready to be driven into the pile holes.

August 2019

Parliament Square’s full construction schedule has been confirmed.

In the most recent update from the developer of Parliament Square, we have been informed that the team are now being set up on-site in preparation to commence construction works.

 

Summary of Works Progressed

• Excavation works completed.
• A full schedule has been put in place.

 

Works Scheduled

• Commence the bulk dig involving removing, adding and moving rock and soil around the site to achieve a suitable height for construction.
• Piling with the contiguous walls, a deep foundation part of the groundworks to help form a watertight retaining wall.
• Commence the main groundworks package.
• Concrete frame installation.

May 2019

Work has begun at Parliament Square in Liverpool, with the first construction update showing that the hoarding has been successfully erected around the site.

The area is undergoing various preparations. Extensive site investigations entailing numerous collections of data and reports have now been completed. Excavation has commenced which involves works to the earth, such as trenching and tunnelling underground.

 

Summary of Works Progressed

• The hoarding has been 100% erected.
• 100% of site investigation works have been completed.
• Excavation works have commenced.

 

Works Scheduled

• Completion of excavation works.
• Sewage and drainage work to commence.

2022

Parliament Square has seen sufficient construction progress over the last period to Blocks B and D.

There has been progression to Block D’s retaining walls and concrete beam foundations and the internal staircase structure has commenced. Block B fire coating of the steel framework is now complete and window installation is nearing completion.

Summary of Works Progressed – Block B

  • Completion of fire coating steel framework
  • Sub-structure masonry wall is 55% complete
  • Finalisations to structural framework forming external walls
  • Finalisations to weatherboarding
  • Completion of above ground drainage
  • Finishing touches to structural framework forming external walls
  • Window installation is 97% complete
  • Clear progressions to brickwork elevations
  • 77% completion of apartment ceiling installation
  • Commencement of cladding installation
  • Completion of mast climber installation
  • Partition walls installation now 93% complete
  • Plaster finishes walls and ceilings is 67% complete
  • 70% completion of 1st fix electrical, plumbing and heating
  • Rapid progression of kitchen units and appliances
  • Doorframes are 65% complete with skirting and architrave 60% complete
  • Bathroom sanitary fittings 52% progressed
  • Wall and floor tiling as well as carpet and floor finishes are 61% complete
  • Doors and ironmongery 51% complete
  • 2nd fix electrical, plumbing and heating all 29% complete

2021

In Block B, the structural framework forming the external walls is 93% progressed. Block D retaining walls and concrete beam foundations are underway.  

Works have progressed both internally and externally to Block B, which now sees the flat roof structure and covering 95% progressed, whilst brickwork to elevations has commenced. In Block D, piles have been cropped ready for removal from site, and Eazistrip reinforcement continuity systems are onsite ready for installation.  

Summary of Works Progressed – Block B 

  • Sub-structure masonry wall is 45% complete 
  • Structural framework forming external walls is 93% complete 
  • Fire coating to the steel framework is complete 
  • The flat roof structure and covering is making great progress and is now 95% progressed 
  • Podium steel structure and concrete pour 100% complete 
  • Weatherboarding is 93% progressed so far 
  • Window installation is also underway and 93% complete 
  • Brickwork to elevations has commenced 
  • Riser installation is 65% complete 
  • Partition walls  are 72% progressed 
  • Apartment ceilings are 73% complete 
  • Plaster finishes to walls and ceilings are ongoing 
  • 1st fix electrical works are 46% progressed and 1st fix plumbing and heating are 45% complete 
  • Kitchen units and appliances are being installed 
  • Doorframes are 32% progressed with skirting and architrave 23% complete. Doors and ironmongery commenced 
  • Bathroom sanitary fittings 16% progressed 
  • Wall and floor tiling is 27% progressed with carpet and floor finishes also ongoing 
  • 2nd fix electrical, plumbing and heating underway 

Summary of Works Progressed – Block D 

  • Retaining walls and concrete beam foundations are 5% complete 
  • Pile foundation load testing underway 
  • Steel reinforcement mesh, drainage, concrete manhole rings and other materials have arrived on site 
  • Shuttering in place for the contiguous wall concrete pour 
  • Steel cage reinforcement formed 
  • Eazistrip reinforcement continuity systems onsite ready  for installation 
  • Piles cropped ready for removal off site 
  • Formation of reinforcement for pile capping beams has commenced 
  • Steel reinforcement to the party wall 
  • Reducing of levels is ongoing 

Block A is now officially completed. Block D demolition continues whilst Block B sprinkler and first fix mechanical have commenced.

Work carries on across Blocks B and D as the development takes shape more and more every week.

Summary of Works Progressed – Block A

  • Flat roof coverings including balconies are 100% complete
  • External windows, doors and curtain walling are 100% complete
  • Brickwork and insulation complete
  • External wall cladding is completed
  • Inspection of works to completed apartments is complete
  • Carpet and floor finishes complete
  • Decorations are complete
  • Second fix works are complete
  • General fixtures and fittings are complete
  • This block is now 100% completed

Summary of Works Progressed – Block B

  • Concrete pour to upper suspended floor structure has been completed
  • Fire coating to steel framework is now 85% complete
  • Structural framework forming the external walls is 80% progressed
  • The podium steel structure is 95% complete
  • The podium concrete pour is also nearly complete at 95% progression so far
  • First fix mechanical has commenced
  • Sprinkler system commenced
  • Window installation ongoing

Summary of Works Progressed – Block D

  • Demolition and site clearance are 50% progressed

Many tasks have been completed this month at Parliament Square, including weatherboarding, above ground drainage and plaster finishes in Block A and the upper suspended steel floor structure is approaching completion in Block B.

Internal progress has made headway in Block A including the installation of kitchen units, doorframes, carpets and second fix electrical works. In Block B, fire coating to the steel framework has progressed well and the podium steel structure and concrete pour are 95% complete.

Summary of Works Progressed – Block A

  • Weatherboarding, above ground drainage, plaster finishes, partition walls, apartment ceilings and wall and floor tiling have all completed
  • Flat roof coverings including balconies are 95% complete
  • External windows, doors and curtain walling are 98% complete
  • Brickwork and insulation to elevations is 80% complete
  • External wall cladding is 25% progressed
  • The lift installation is nearly complete
  • Kitchen units and appliances are being installed
  • Doorframes are 95% complete
  • Skirting and architrave are 89% progressed so far
  • Bathroom sanitary fittings are 91% complete
  • Carpet and floor finishes are 69% complete
  • Doors and ironmongery are making great progress
  • Decorations are progressing well and are 85% progressed
  • Second fix electrical works are 86% progressed with plumbing and heating 67% complete
  • General fixtures and fittings are ongoing and are 21% complete thus far

Summary of Works Progressed – Block B

  • Upper suspended steel floor structure 90% complete
  • Concrete pour to upper suspended floor structure is 90% complete
  • Fire coating to steel framework is 40% complete
  • Structural framework forming the external walls is 12.5% progressed
  • The podium steel structure is 95% complete
  • The podium concrete pour is also nearly complete at 95% progression so far
  • Window installation commenced

February 2021

Block B concrete pour continues whilst Block A is making great internal progress.

In Block B, the steel frame structure is now complete and the concrete pour to the upper suspended floor structure is underway. In Block A, several tasks are approaching completion including flat roof coverings, weatherboarding, and external windows. First and second fix works are making excellent progress as well as other internal fit out works.

 

Summary of Works Progressed – Block A

  • Flat roof coverings and balconies are 95% complete.
  • Weatherboarding nearly complete at 99% progressed.
  • External windows, doors and curtain walling is 98% progressed.
  • Brickwork and insulation to elevations is 45% complete.
  • External wall cladding is commenced and 5% progressed so far.
  • Lift installation is 65% complete.
  • Above ground drainage is 85% progressed.
  • Partition walls installation has made good progress and is 92% complete.
  • Apartment ceiling installation, first fix electrical, plumbing and heating are all 85% complete.
  • Second fix electrical, plumbing and heating are 40% complete.
  • Plaster finishes to walls and ceilings are 60% progressed.
  • Door frames, skirting and architrave are all halfway there.
  • Kitchen units and appliances are 55% complete.
  • Bathroom sanitary fittings are 45% progressed.
  • Wall and floor tiling are 60% progressed with carpet and floor finishes now 40% complete.
  • Doors and ironmongery are ongoing at 10% progression so far.
  • Decorations are 35% complete with general fixtures and fittings underway.

 

Summary of Works Progressed – Block B

  • Steel frame structure 100% complete.
  • Floor slab construction 100% complete.
  • Retaining walls and concrete beam foundations 100% complete.
  • Internal staircase structure 100% complete.
  • Concrete pour to upper suspended floor structure 66% complete.

2020

November 2020

Block A is progressing well, and construction of Block B has commenced.

Block B has received foundation works and concrete pour, as well as the steel frame delivery which has since commenced.

Summary of Works Progressed – Block A

  • Scaffolding complete
  • Internal staircase structure completed
  • Structural framework forming the external walls is 100% complete
  • Weatherboarding has made huge progress to 85% completion
  • Flat roof covering is 50% progressed
  • Sub-structure masonry walls are 40% complete
  • Internal partition walls are 40% complete
  • Mechanical services are 25% complete
  • Riser installation is ongoing
  • Core drilling services are almost complete
  • Window installation is 60% complete
  • Brickwork to elevations has commenced
  • Apartment ceiling installation has commenced and is 10% progressed so far

Summary of Works Progressed – Block B

  • Excavations and cage reinforcement concrete foundations
  • Reinforcement cages for pad foundations
  • Concrete foundations poured
  • Site clearance
  • Floor slab preparation
  • Concrete floor slab poured
  • Site preparation for steel frame delivery
  • Steel frame structure now 90% complete

August 2020

Construction works have been primarily to Block A with the steel frame structure now complete.

Other tasks completed include underground drainage, the internal staircase structure and floor slab construction.

Summary of Works Progressed

  • Site compound and supplies 100% complete.
  • Ground infill and site levelling complete.
  • Piling foundations complete.
  • Retaining walls and concrete beam foundations complete.
  • Underground drainage is complete.
  • Floor slab construction 100% complete.
  • Steel frame structure complete to Block A.
  • Upper suspended steel floor structure complete.
  • Internal staircase structure complete.
  • Fire coating to the steel framework is complete.
  • Structural framework forming external walls 20% progressed.
  • Internal partition walls 25% complete.
  • Mechanical services 5% complete.
  • Hoist installed.
  • Scaffolding commenced.
  • Temporary electrical supply installed.

May 2020

Parliament Square has seen great progress made to the basement car park, floor slab construction and Block A’s steel frame structure.

Other activities commenced during this time include further work to ground infill and levelling which is nearly 100% complete, progress to the retaining walls, pre-cast concrete staircases and the installing of easi-edge handrail system.

Summary of Works Progressed

  • Site compound and supplies 90% complete.
  • Significant progress to the steel frame structure on Block A which is 25% complete.
  • Steel reinforcement concrete slab and column structures 35% progressed.
  • Floor slab construction commenced 30%.
  • Further progress to ground infill and levelling which are 98% complete.
  • Retaining walls and concrete beam foundations progressed 60%.
  • Retaining walls and foundations to the basement car park.
  • Pre-cast concrete staircases installed.
  • Metal deck suspended and upper floor materials loaded.
  • Easi-edge handrail system installed.

February 2020

Ground infill is 90% progressed at Parliament Square with piling foundations 100% complete.

The progress at Parliament Square during this construction period has seen the formation of concrete retaining walls and steelwork has been put in place ready for the construction of columns.

Summary of Works Progressed

  • The site compound and temporary supplies are 50% complete with site floodlights and a site washdown cleaning facility now installed.
  • Ground infill and site levelling is nearly completed at 90%.
  • Piling foundations are 100% complete with piled retaining concrete walls formed.
  • Concrete retaining walls have progressed by 10% and service ducts have been formed in the walls. The retaining walls have been waterproofed.
  • Concrete beam foundations have commenced and are 10% complete.
  • Steelwork has been put in place for column construction and concrete pads have been formed to support these columns.
  • The crane pad is under construction.
  • Excavation to the sandstone car park base.

 

Works Scheduled

  • Construction of columns.

2019

November 2019

With demolition complete, construction has begun at Parliament Square in Liverpool and work is progressing nicely.

There has been significant construction activity to the sub-structure and super-structure during the latest period, including the ground being infilled and levelled, and the progress of pilings and concrete foundations.

 

Summary of Works Progressed

• Demolition is now complete.
• Site clearance is 100% complete.
• Trial pit areas were marked out and dug as part of ground investigations.
• The site compound and temporary supplies have progressed by 50%.
• The ground is being infilled and levelled which has made great progress of 80%.
• Pilings and the concrete foundations have progressed by 60%. The pile foundation has formed the retaining wall.
• Reinforced steel cages are on site and prepared.

 

Works Scheduled

• Reinforced steel cages ready to be driven into the pile holes.

August 2019

Parliament Square’s full construction schedule has been confirmed.

In the most recent update from the developer of Parliament Square, we have been informed that the team are now being set up on-site in preparation to commence construction works.

 

Summary of Works Progressed

• Excavation works completed.
• A full schedule has been put in place.

 

Works Scheduled

• Commence the bulk dig involving removing, adding and moving rock and soil around the site to achieve a suitable height for construction.
• Piling with the contiguous walls, a deep foundation part of the groundworks to help form a watertight retaining wall.
• Commence the main groundworks package.
• Concrete frame installation.

May 2019

Work has begun at Parliament Square in Liverpool, with the first construction update showing that the hoarding has been successfully erected around the site.

The area is undergoing various preparations. Extensive site investigations entailing numerous collections of data and reports have now been completed. Excavation has commenced which involves works to the earth, such as trenching and tunnelling underground.

 

Summary of Works Progressed

• The hoarding has been 100% erected.
• 100% of site investigation works have been completed.
• Excavation works have commenced.

 

Works Scheduled

• Completion of excavation works.
• Sewage and drainage work to commence.

Future Completed Project Visualizations

parallax-image

Invest in Parliament Square

View Property Details

Refer a Friend to RWinvest

Have you heard about our referral scheme? With our referral scheme, you can be rewarded by simply recommending a fellow investor to RWinvest.

Each time you refer someone to our properties, and they go on to make a sale, you’ll earn £500. It’s one of the easiest ways to generate a quick cash boost on top of your lucrative investment earnings!

If you have a friend or family member who’s thinking of buying an investment property, and you’re happy with the service you experienced with us, get in touch with us today to find out how to get involved with our referral scheme.

Liverpool L1 City Centre Postcode

The Mill

Invest From £39,950

Liverpool Prices from £139,950

Assured 6% NET Rental Return

Grade 2 Listed Building

Exclusive Payment Structure

One Park Lane

Exclusive Liverpool Investment

Liverpool Prices from £129,950

6% Assured Net Rental Return

16 Storey Skyscraper

Invest With £29,990

Heaps Mill

Exclusive RWinvest Opportunity

Liverpool Prices from £124,950

7% Assured Net Rental Return

Deposits From as Little as 15%